Temario:

How can a customer get access to SAP Cloud ALM? Please choose the correct answer. SAP Cloud ALM can be bought on the SAP Store. SAP Cloud ALM fair usage rights are included in SAP Preferred Success and SAP Preferred Care at NO additional cost. SAP Cloud ALM fair usage rights are included in SAP Enterprise Support, cloud editions at NO additional cost. SAP Cloud ALM fair usage rights are included in SAP MaxAttention and SAP ActiveAttention at NO additional cost.

In SAP Activate, what tool is used in the agile delivery approach during the Realize phase to make forecasts based on actual data? Please choose the correct answer. Product backlog. Release plan. Scrum board. Burndown chart.

In which phase do you create 'an ordered list of everything that is known to be needed in the product'? Please choose the correct answer. Explore. Discover. Realize. Prepare.

In which phase do you run the user acceptance test? Please choose the correct answer. Deploy. Build and Test. Final Preparation. Realize.

In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps? Please choose the correct answer. Prepare. Deploy. Explore. Realize.

In which phase of SAP Activate does the SAP Project Manager set up project governance? Please choose the correct answer. Discover. Realize. Explore. Prepare.

The hypercare period is part of which phase? Please choose the correct answer. Realize. Deploy. Go-Live. Explore.

What accelerator can help you document the configuration definition in the Explore phase? Please choose the correct answer. Data definition. Backlog template. Business Blueprint document. Business Driven Configuration Questionnaire.

What activities do you perform during the fit-to-standard workshops milestone in the SAP Activate methodology within SAP Cloud ALM? There are 3 correct answers to this question. Create wireframes for user interfaces in SAP Cloud ALM. Create notes and/or requirements in SAP Cloud ALM. View details of high-level process flows in SAP Cloud ALM. Create SAP Fiori screen mock-ups in SAP Cloud ALM. View details of business process diagrams and descriptions in SAP Cloud ALM.

What activity do you perform in the Deploy phase? Please choose the correct answer. Perform productive cutover. Final assessment of data quality. Complete integration testing. Implement operations processes.

What are key goals of the burndown chart? There are 2 correct answers to this question. Assignment of backlog items to future sprints up to the completion of the release. Determination of the planned go-live date based on current velocity. Visualization of the size of the backlog consumed so far. Determination of the overall availability of the team for future sprints.

What are potential use cases for SAP Cloud ALM? There are 2 correct answers to this question. Upgrading SAP Success Factors. Upgrading SAP S/4HANA Public Edition. Implementing Tricentis Test Automation. Implementing SAP Ariba.

What are some core objectives of business process monitoring? There are 2 correct answers to this question. To provide process update and change feedback. To provide transparency over end-to-end processes. To increase business process execution quality. To provide reverse business process analysis.

What are some of the key characteristics of the implementation approach in the SAP Activate methodology? There are 2 correct answers to this question. Cloud ready. Based on ready-to-use content. Fixed scope. Scaled agile framework built-in.

What are some of the key topics covered in the Customer Team Enablement workstream? There are 2 correct answers to this question. Technology and architecture expertise. Project management expertise. Process benchmarking expertise. Business process expertise.

What are some of the values of SAP Cloud ALM for implementation? There are 3 correct answers to this question. Accelerated time to market. Pre-loaded SAP Activates tasks. Central cost and effort management. Comprehensive document repository. NO additional cost of product.

What are some of the values of SAP Cloud ALM for operations? Note: There are 3 correct answers to this question There are 3 correct answers to this question. It provides a solution readiness check. It provides license management capabilities. It provides improved efficiency and automation. It provides end-to-end transparency. It provides reduced cost of operations.

What are the capabilities of the Task Management application in SAP Cloud ALM with SAP Activate methodology tasks? There are 3 correct answers to this question. Launch SAP Cloud ALM apps to perform SAP Activate task. Create sub-tasks to break down the SAP Activate task. Assign SAP Activate task to a team member. Delete SAP delivered SAP Activate tasks. Change the description of the SAP Activate task.

What are the core capabilities in SAP Cloud ALM for implementation? There are 3 correct answers to this question. Custom code management. Test management. Task management. Process management. Portfolio management.

What are the core capabilities of SAP Cloud ALM for operations? There are 3 correct answers to this question. Event and alert management. Upgrade analysis. Operation automation. License management. Monitoring.

What are the outcomes of business process monitoring? There are 2 correct answers to this question. To improve business process KPIs. To provide process update and change feedback. To increase business process execution quality. To provide transparency over end-to-end processes.

What are the SAP Cloud ALM Implementation capabilities? There are 2 correct answers to this question. Perform implementation activities. Check data quality prior to migration. Monitor project performance centrally. Natively built-in test automation.

What capabilities does SAP API Business Hub provide to help you select integration options for your project? There are 3 correct answers to this question. Advice on selecting scope items in SAP Best Practices Explorer. Sandbox for testing APIs. Recommendations on using integration bus (SAP Process Orchestration or SAP Integration Suite). Integration with IDE and code generation. Pre-packaged integrations.

What does a cutover involve? There are 2 correct answers to this question. Completing solution end-user documentation. Aligning business and technical cutover plans. Presenting completed functionality to key users. Switching productive operations to new system.

What information does the project team need before they can correctly estimate the relative size of backlog user stories? Please choose the correct answer. Overall project schedule. Available project resources. Test strategy. Definition of Done.

What information does the Scrum team need before they can correctly estimate the relative size of backlog user stories? There are 2 correct answers to this question. Anchor user story in the backlog. Definition of Ready. Number of backlog user stories. Definition of Done.

What is a strategy level 0 (LO) artifact? Please choose the correct answer. Optional information that is NOT important for project activities. Project result that is developed solely by the partner. Preliminary strategy developed by the customer to approach the project in a specific area. Approach document that is developed by a united project team (partner + customer).

What is an activity that is performed at the end of the Realize phase? Please choose the correct answer. Load data into a production system. Provision development system. Run the user acceptance test. Perform cutover simulation.

What is Scrum of Scrums? Please choose the correct answer. Mechanism for gathering and validating requirements. Alternative to regular Scrum process for smaller teams. Integration meeting among the various Scrum teams. Frequent inspection of code and configuration prior to quality gates.

What is the basis for approving work results (signing Act of Acceptance) on Project Phase level? Please choose the correct answer. Definition of Done for Sprint. Steering committee meeting decision. Definition of Done for User Story. Agreed and met Acceptance Criteria within quality gate.

What is the key difference between Notes and Requirements in the Change and Deploy capability of SAP Cloud ALM? Please choose the correct answer. Users can create a follow-up task that is actionable for Requirements. Notes are created from tasks. Requirements are created from tasks. Users can create a follow-up task that is actionable for Notes.

What is the objective of a Sprint Retrospective meeting? Please choose the correct answer. Prioritize the remaining backlog items. Provide feedback to the project sponsor. Prepare for Quality Gate. Improve the team's process.

What is the purpose of 'Scrum of Scrums'? Please choose the correct answer. To create an alternative Scrum process for larger teams. To run an integration meeting across the various teams. To conduct a regular review of risk and issues. To gather requirements from business users.

What is the purpose of the scrum board? Please choose the correct answer. To manage the scrum resources load. To represent the scrum team setup. To represent the work. To visualize scrum team progress.

What is the result of fit-to-standard workshops? Please choose the correct answer. Preparation of standard test cases and test scripts for end users. Prioritization of the requirements backlog by the team. Confirmation solution fit and identification of delta requirements. Detailed assessment of customer's current business processes.

What should the project team consider when defining their sprint duration and cadence? There are 2 correct answers to this question. Adjust sprint duration based on team availability. Set variable sprint duration based on work. Establish fixed duration of each sprint. Sprint duration between 1 week to 4 weeks.

What solution operations framework can customers use to create a joint business and IT organization? Please choose the correct answer. Solution Standardization Board. SAP Roadmap Explorer. Customer Center of Expertise. Transformation Management Office.

When do you perform Quality Gate (Q-Gate) during a project? There are 2 correct answers to this question. At the end of Discover phase. At the end of Realize phase. At the end of Prepare phase. At the end of Run phase.

When does the product owner accept or reject the user stories included in the Sprint? Please choose the correct answer. During the Quality Gate. During the Sprint Review. During the user acceptance test. During the daily Scrum meeting.

When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer. During the daily Scrum meeting. During the Sprint Review. During the Sprint Retrospective. During the user acceptance test.

Where can you find data migration templates? Please choose the correct answer. SAP Best Practices Explorer. Roadmap Viewer. SAP S/4HANA migration cockpit. SAP Cloud Appliance Library.

Where can you find the Integration Content? There are 3 correct answers to this question. SAP Solution Manager. SAP Cloud Appliance Library. SAP Best Practices Explorer. SAP API Business Hub. Cloud Integration Automation service.

Where do you activate SAP Best Practices from Cloud ALM to be used during the fit-to-standard workshops for SAP S/4HANA Cloud Public Edition? Please choose the correct answer. Starter System. Quality System. Development System. Production System.

Which accelerators support the fit-to-standard workshop in the Explore phase? There are 2 correct answers to this question. Business Process Design Template. Quality Gate Checklist. Test Strategy. Backlog Template.

Which applications include content for integration scenarios? There are 2 correct answers to this question. SAP Signavio Process Navigator. SAP Business Accelerator Hub. SAP Cloud Appliance Library. SAP Solution Manager.

Which artefacts in the Testing workstream are created within the Realize phase? There are 2 correct answers to this question. User Acceptance Test - Plan. Functional Specifications. Test Strategy. Functional Test Scenarios.

Which artifacts are part of the Solution Adoption workstream? There are 3 correct answers to this question. Change Management Roadmap. End User Learning Needs Analysis. Detailed Design - Business Process. Learning Content. Project Plan.

Which artifacts in the Testing workstream are created within the Realize phase for the "New Implementation of SAP S/4HANA Cloud"transition path? There are 2 correct answers to this question. User Acceptance Test. Functional Specifications. Functional Test Scenarios. Reporting Functional Specifications.

Which estimation technique can be used in an Agile delivery approach to size the User Stories during sprint planning? Please choose the correct answer. Detailed top-down estimates by the Scrum Master in story points or Ideal Person Days. Leveraging effort estimates for similar User Stories from another Scrum team. Relative estimates in Ideal Person Days that reflect the best estimates provided by the project team. Detailed bottom-up estimates that break each User Story into shorter tasks.

Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to waterfall? There are 2 correct answers to this question. Scrum master. Product owner. Integration lead. Design thinking coach.

Which of the following are included in ready-to-use content in SAP Activate? There are 2 correct answers to this question. Project accelerators. SAP Best Practices. Business models from leading companies in each industry sector. Baseline Activation Service.

Which of the following are part of the 10 SAP Quality Principles? There are 2 correct answers to this question. Start scoping early. Use standard functionality. Achieve production readiness. Plan one phase at a time.

Which of the following are the benefits of using ready-to-use content? There are 2 correct answers to this question. Fast time-to-value. Predictable results. Maximized total cost of ownership. Exhaustive solution documentation.

Which of the following belong to the Application Design and Configuration workstream for SAP S/4HANA Cloud in the Explore Phase? There are 2 correct answers to this question. Integration prerequisites confirmation. Fit-to-standard workshop. Configuration definition. Kick-off workshop.

Which of the following belongs to the Application Design and Configuration workstream in the Explore phase? There are 2 correct answers to this question. Integration prerequisites confirmation. Fit-to-standard workshop. Configuration definition. Change Impact Analysis.

Which of the following is a key characteristic of the Agile Please choose the correct answer. Formal and detailed documentation. Iterative build with frequent inspections. Frequent quality gates. Frequent and detailed project scheduling.

Which of the following is part of the Explore phase for new implementations? There are 2 correct answers to this question. Customer self-enablement. Fit-to-standard. Data load preparation. Cutover plan.

Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud" transition path? Please choose the correct answer. Setup and enablement. Solution validation and Delta design. Simplification and custom code impact analysis. Fit-to-standard.

Which techniques should the SAP Activate practitioner follow? There are 3 correct answers to this question. Leverage dynamic extensibility and integrations. Optimize testing by running it only at the end of Realize phase. Reduce business user involvement for efficiency. Use agile approach throughout the project. Apply the fit-to-standard first mindset.

Which tools can SAP Cloud ALM leverage for project tasks? There are 2 correct answers to this question. SAP Solution Manager. SAP Central Business Configuration. SAP Readiness Check. SAP Signavio Process Navigator.

Working in an Agile approach, what should your planning look like at the beginning of the Realize phase? Please choose the correct answer. Project scope and planning are completed and final. User Stories are in Ready state for only the first 2 to 3 sprints. Scope and duration of testing are finalized. Durations of all sprints for the full release are defined based on planned complexity.

You are defining the testing strategy for your project. What would you include in a scope of Integration Test? There are 2 correct answers to this question. Interfaces with other applications. Functionality of end-to-end business processes. Connectivity between database and application servers. Quality of data for migration.