According to the Definition of Done, which activity must be completed for each sprint? Please choose the correct answer Functionality must be released to the business End user training must be delivered Solution must be built and configured in the development system (DEV) Functionality must be tested in the Quality system (QAS). .
Arrange the following in the correct sequence of steps followed for a 'Fit to Standard' workshop. Please choose the correct answer Demonstrate Business Scenarios and Concepts, Review Best Practice Process Flow, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Discuss how the process fit with customer requirements, Identify gaps, Identify required configuration, Enable customer on execution of scenarios Discuss how the process fit with customer requirements, Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Enable customer on execution of scenarios, Identify gaps Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps.
How are the build and test tasks planned and executed in the Realize phase? Please choose the correct answer With Q-Gates for sign off after each iteration By using the sprint backlog list as input for each iteration By using incremental build in fixed-scope iteration By executing regression tests after each iteration. .
How can SCRUM teams be organized? By project governance level By project phase By work stream By job title. .
How can the project manager help to keep momentum in the project and help to keep the customer involved? There are 2 correct answers to this question Add customer resources to the project to reduce the need for formal training Leverage agile cycles to build and test the solution Increase the number of Q-Gates Walk through the solution processes with the stakeholders. .
How do you gain access to the SAP Activate Methodology Jam site? Please choose the correct Send e-mail to SAP contact address Submit e-mail address via on-line form Join SAP S/4HANA group on SAP Community Network Register on SAP Service Marketplace. .
How many deliverables are a part of the Key Deliverable 'Project Initiation'? Please choose the correct answer 1 2 3 4.
How would you describe the Realize phase in the new implemetation the SAP S/4HANA? Transition Path Configure and Develop Configure Configure and Adjust custom code .
How often will an upgrade be performed on SAP S/4HANA Cloud Single Tenant Edition enviroment? Every year One Upgrade and two Feature Packages by year Every Quarter Scheduled is defined by Service Level Agreement for SAP HANA Enterprise Cloud and SAP HANA Cloud Tenant Edition Service .
Identify the two landscape transformation specific tasks in the explore phase. There are 2 correct Setup Landscape Transformation Software Define the Data Migration Architecture Run a Landscape Transformation Assessment Perform Client transfer. .
In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the correct answe Business Process Mapping Value Determination Fit/Gap Workshops Custom Extension management. .
In SAP Activate, what tool is used in the Agile Delivery Approach during the Realize Phase to make forecast based on actual data? Release planning. Product Increment Burndown chart Product Plan .
In the context of Scrum, which of the following statements are correct? 2 answers Product Backlog is a list of features prioritized by business value, the items come from diverse sources, including the Scrum team. Sprint backlog is a subset of product backlog loaded onto the sprint's "timebox", it is the list of work the team is addressing during the current sprint. Burndown chart provides visibility into the product backlog, illustrate progress by the team, work is in horizontal and time is in the vertical. .
In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included? Please choose the correct answer Final testing Interface setup Scheduling project plan Hyper care support. .
In what respect is SAP Activate Methodology different from the ASAP Methodology? Please choose the Leverages iterative incremental build Supports only new implementations Includes Fit/Gap analysis instead of Blueprint Supports cloud deployments. .
In which of the following project phases is it important to plan and schedule data loads followed by load validation activities? Please choose the correct answer Realize Explore Prepare Deploy. .
In which phase do you create a prioritized list of user requirements? Please choose the correct answer Explore Deploy Prepare Realize. .
In which phase do you verify that the SAP Best Practice solution scenarios meet the business needs of the customer? Please choose the correct answer Explore Deploy Prepare Realize. .
In Which phase does the Transition to Operations work stream start? Please choose the correct answer Explore Deploy Prepare Realize. .
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal? Please choose the correct answer Explore Deploy Prepare Realize. .
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer Explore Deploy Prepare Realize. .
In which phase of the SAP Activate methodology does the team complete the Transformation Planning? Please choose the correct answer Explore Deploy Prepare Realize. .
In which phase you execute the User Acceptance Test? Please choose the correct answer Deploy Final Preparation Build and Test. Realize .
In which SAP Activate methodology phase does the team complete the Integration Validation? Please choose the correct answer Prepare Explore Deploy Realize. .
In which SAP Activate methodology phase does the team complete the Transformation Strategy? Please choose the correct answer Deploy Prepare Explore Realize. .
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the correct answer Deploy Prepare Explore Realize. .
In which phase should you first run the Readiness Check for SAP S/Hana selective Data Transition path in a system cosolidation scenario tha includes convertion from SAP ERP? please choose the correct answer Discover Prepare Explore Realize. .
In which tools can the project team across the SAP Activate Methodology content including accelerators? There are 2 correct answers to this question Roadmap Viewer SAP Community Network SAP Jam SAP Service Marketplace. .
Regarding user stories and releases, which of the following statements are correct? Choose the 3 correct answers. A user story is a tool used in Agile Software development to capture a description of a software feature from an end-user perspective.The user story describes the type of user. what they want and why. A user story helps to create a simplified description of a requirement. A release is a deployable sofware package that is the culmination of several iteractions. Releases can be made before the end of an iteration. .
SAP now offers the ability to deploy and manage solutions in which of the following environments? Please choose the correct answer Cloud and On-premise On-premise Cloud, On-premise and Hybrid. Cloud .
The tasks associated with Landscape transportation are in which workstream? Please choose the correc answer Technical Architecture and Infrastructure Application Solution Adoption System & Data Migration Transition to Operations. .
What are deliverables of the Application: Integration work stream in the prepare phase? There are 3 correct answers to this question Fit/Gap Analysis Adaptation Specifications Network Connectivity Checks Data Cleansing Security Checks.
What accelerator can help you document the Configuration Definition in the Explore Phase? Choose the correct answer Data Definition Changue Request Template Backlog Templates Test strategy. .
What are key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question Validate solution Premium engagement ready Fixed scope Start with SAP Best Practices On-premise only. .
What are SCRUM of SCRUMS? Please choose the correct answer Alternative to regular SCRUM process for smaller teams Mechanism for gathering and validating requirements Integration meeting between the various project teams Frequent inspection of code and configuration prior to quality gates. .
What are some characteristics of the "Cloud" mindset? There are 3 answers Make the company fit the software Heavy customizations and modifications Business blueprint phase Workrounds and light extensions Fit-to-Standard workshop .
What are some of the key topics covered in the custumer team enablement workshops? There are three answers Technical expertise Project management project sourcing approach Solution Expertise Planning Skills .
What are the benefits of the SAP best practices? There are 3 correct answers to this question Reduced functional scope Fast time to value Simple on-boarding to cloud Predictable results Fixed organizational structure. .
What are the responsibilities of the Product Owner in release and sprint planning? There are 2 correct Analyze the functional and technical dependencies between the user stories Define objectives for each release Prioritize backlog user stories by business priority Estimate the backlog user stories. .
What are the responsibilities of the Project Team on level 4 ? There are 2 correct answers to this question Identify and resolve issues and risks Perform status reporting and communication Set business priorities, goals and objectives Set Project policy, standards and oversight. .
What are the three elements of SAP Activate? There are 3 correct answers to this question Content Methodology Focuses Build Tools SAP Solution Manager .
What are the three pillars of SAP Activate? There are 3 correct answers to this question Guided Configuration SAP Activate Methodology SAP S/4HANA in-memory database SAP Solution Manager SAP Best Practices. .
What are two important approaches based on the Control Center Concepts that SAP Solution Manager for The premiun Engaement Service? 2 answers Run SAP like a Factory Built SAP Like a Factory Intelligent Enterpeise .
What can users do in the Roadmap Viewer tool? Please choose the correct answer Display and navigate detailed SAP Activate methodology WBS Download full SAP Activate methodology content for use off-line Upload SAP Activate WBS into SAP Solution Manager7.1 Create a customer-specific version of SAP Activate Methodology. .
What can you do in the SAP Roadmap Viewer Tool? please choose the correct anwer Download full roadmap content for offline navigation Coment on Deliverables and Tasks within Roadmaps Navigated detailded solution Implentation Roadmaps Create a customer-specific version of roadmap .
What criterion does the product owner use to Sequence the Product Backlog? Please choose the correct answer Business Priority Resource availability Compatibility Minimun Input .
What do you do during an iterative approach to build a solution? Please choose the correct answer Include frequent inspection check-points Build the solution module by module Provide a working solution only at the end of the release Deliver a prototype of the solution. .
What do you do during post cutover? Please choose the correct answer Perform the Verification Session of the SAP Going Live Check Setup Operational Support Conduct Organizational Readiness Check Perform Technical System Test. .
What do you do during Sprint Execution? Please choose the correct answer Present status of selected user stories in the sprint scope on a scrumboard Hold a retrospective at the end of each week End a sprint when the sprint backlog items are all complete Measure the sprint progress with a percentage complete report. .
What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition? Please choose the correct answer Full project SCRUM SAP Best Practices Project team training Rapid prototyping. .
What does SAP Activate recommend to keep team members informed and aligned? Please choose the correct answer Daily e-mail status updates to project manager Daily team stand-up meeting Daily progress review meeting with sponsor Daily status meeting with project manager. .
What information does the product team need so that they can estimate the relative size of backlog user story correctly? Please choose the correct answer Definition of Done Available project resources Overall project schedule Test strategy. .
What is a benefit of using Guided Configuration instead of the Implementation Guide? Please choose the correct answer It ensures SAP updates do NOT conflict with customer configurations It ensures configuration is done using SAP Solution Manager It eliminates the need for Content Lifecycle Management It eliminates the need to generate transport requests for configuration settings. .
What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate? Pleaso Choose the correct answer Project Charter Learning plan Knowledge transfer to end users Project Documentation. .
What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise? Please choose the correct answer For on-premise, there is an additional Q-Gate for system installation For the cloud edition, there is an additional Q-Gate for integration with on-premise systems For on-premise, there are additional deliverables for the system setup For the cloud edition, there is an additional work stream for integration with on-premise systems. .
What is the difference between the "System Conversion" and "The new Implementation" of SAP HANA transition path? 2 answer There are different upgrade cycles In the Realize Phase custom code is adjusted rather than deliberables for System Convertion In the Realize phase data isconvertedand Not migrated for system converstion SSCs are used in the system conversion for configuring SAP S/4HANA throught the Manage Solution APP .
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer Limited involvement of business stakeholders Waterfall approach Start with executable content Design-based. .
What is SAP Activate? Please choose the correct answer A step-by-step instruction on how to remove from SAP best practices to your custom solution A combination of SAP best practices , methodology, and guided configuration A methodology for each of the deployment modes (cloud , on-premise, hybrid) A bundle of ASAP , SAP Launch , and Rapid Deployment Solutions. .
What is the basis for approving work result (signing act of acceptance) on a project phase level? choose the correct anwer Definition of Done for user story SCRUM of scrums meetings decision Definition of ready for sprint Agreed and met acceptance criteria within quality gate .
What is the best target environment for a System Conversion journey is as described in the SAP Activate methodology? Please choose the correct answer SAP Hybris SAP S/4HANA Cloud Edition Hybrid of SAP S/4HANA Cloud Edition and SAP S/4HANA On-Premise Edition. SAP S/4HANA On-Premise Edition .
What is the final activity in the Realize phase of a new implementation of SAP S/4HANA cloud edition? Please choose the correct answer Data migration Solution validation Readiness check End-to-End walkthrough. .
What is the correct order of the SAP Activate Methodology phases? Plan => Buid=> Run=> Sustain Discover => Prepare => Explore => Realice => Deploy => Run Plan => Design => Build => Operate Prepare =>Discover => Explore =>Realice => Deploy =>Run .
What is the focus of a SCRUM of SCRUMS in an Agile context? Please choose the correct answer Best Practice adoption Backlog management Communication to the Project Management Office Integration topics. .
What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-premise? Please choose the correct answer Key Deliverable Scenario Task Work Stream. .
What is the key characteristic of Agile project delivery? Please choose the correct answer Frequent Quality Gates Frequent and detailed project scheduling Iterative build with frequent inspections Formal and detailed documentation. .
What is the minimum number of quality gates mandated by the SAP Activate methodology? Please choose the correct answer 1 2 3 4.
What is the most granular level of the methodology you can view in the Roadmap Viewer? Please choose the correct answer Deliverables Task Phase Scenario. .
What is the objective of a sprint retrospective meeting? Please choose the correct answer Review and prioritize the backlog Provide formal feedback to the project manager Define the stakeholder management approach Improve the SCRUM process. .
What is the purpose of a firm-up sprint? Please choose the correct answer To perform sprint testing To revise a release plan and sprint plan To demonstrate functionality from previous sprint To run end-to-end integration test. .
What is the purpose of the SAP Activate Methodology? There are two answers To accelerate the initial implementation of SAP S/4HANA To manage project and solution documentation To provide end-to-end integrated application lifecycle management To enable access to the SAP ecosystem. To provide the sequence of actions in the project.
What is the purpose of the scrumboard? Please choose the correct answer To show the functional breakdown of the solution scope To visualize team progress To document the results of integration testing To manage the resource load. .
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration? Please choose the correct answer To create customer-specific scope items To create delta building blocks for complementary content To activate the Best Practices content To personalize activated, ready-to run business processes. .
What is the purpose of the Solution Validation activity in the Explore phase? There are 3 correct answers to this question To verify technical installation To challenge changes to standard To educate project participants To identify gaps To log additional scope items. .
What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices? Please choose the correct answer Activate and apply SAP Best Practices with SAP Solution Manager Assemble and apply SAP Best Practices to the system Activate and apply SAP Best Practices content with the self-service configuration UI Apply SAP Best Practices with the Configure your Solution application. .
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation? Please choose the correct answer Scope Item Scenario Deliverable Task. .
What technique helps agile project teams to prioritize a large, flat backlog? Please choose the correct answer Planning Poker Retrospective User Story Mapping Fit/Gap Analysis. .
What term is used for a Ready to Run SAP S/4HANA system with pre-fully Solution Documentation which support End-to-End processes for a specific industry so that the Proyect Team can Focus on differentation and innovation? choose the corect answer Fully Activate Apliance SAP Cloud Appliance Library Best Practice adoption SAP Model Company .
What tool do you use to configure an SAP Business Suite on-premise solution? Please choose the correct answer SAP Implementation Guide ABAP Workbench Configuration Composer Expert Configuration. .
What tool provides guidance on replacing custom code development for SAP ERP with SAP S/4HANA functionality for "System convertion" transition Path? SAP Code Inspector Software Update Manager (SUM) with Database Migration option Simplification Item Check (SI-Check) Software Provisioning Manager .
What tool provides shiping estimations ( destinada a identificar si el sistema ECC existente está listo para la conversión a S/4HANA )for the system convertion transition path? SAP BEST Practice Explorer Scope and Effort Analysis SAP READINESS check SAP Transformation Navigator .
What tool would you use for managing project Task and Solutions Documentations when implementing SAP S/4HANA Cloud? SAP Roadmap viewer Implementation Portal for SAP S/4HANA Cloud Sap Transformation Navigator SAP Support Marquetplace .
When do you perform User Acceptance Testing during the Agile Build? Please choose the correct answer After each Sprint During each Firm-up Sprint Before Integration Testing After Integration Testing. .
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer During the sprint retrospective During user acceptance testing During the sprint review During the daily SCRUM meeting. .
Where can you find the Migration Object Template documentation? Choose the correct answer SAP Support Portal SAP Best Practices Explorer SAP Roadmap Viewer SAP Help Portal .
Where can you find Project Library Accelerators? Choose the corret answer SAP Best Practice Explorer Fully Activate Apliance SAP Cloud Appliance Library SAP Roadmap Viewer .
Where can you find the Integration Content? Two correct answers Cloud integration Automation Service Sap Best Practice Explorer SAP API Bussines Hub SAP Solution Manager SAP Cloud Appliance Library .
Via which media does SAP provide Ready-to Run system for SAP S/4 HANA deployment? 2 answer Blu-Ray Disk SAP App Center SAP Solution Builder Tool SAP Cloud Appliance Library .
Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question Quality Gate Checklist RICEF Specification Template Sprint Backlog Template Solution Validation Workshop. .
Which accelerator can help you document the detailed design of solution extensions? Please choose the correct answer RICEF Specification Template Sprint Backlog Template Change Request Template Product Backlog Template. .
Which activities are critical for delivering Agile projects? There are 2 correct answers to this question Sprint planning Retrospective agenda creation Blueprint scheduling Release planning .
Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new implementations? There are 3 correct answers to this question Scope Validation Value Determination Change Management Plan Value Audits Production Support Plan.
Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question Conduct Scope Validation Schedule kick-off workshop Confirm Integration prerequisites Perform Fit/Gap Analysis. .
Which activity helps the project team to add the user stories to the product backlog? Please choose the correct answer Assessing Project Risks Preparing a Project Schedule Conducting the Solution Validation Planning the User Acceptance Test. .
Which activity is part of the SAP Activate Methodology for a new implementation of SAP S/4HANA on-premise edition but NOT of the cloud edition? User Acceptance Test Technical System Test Unit Test End-to-End Integration Test. .
Which artifacts are part of the Solution Adoption Workstream? There are 3 correct answers System Go live Announcement (order) Detailed Designed Business Process Project Plan Business Transformation Review (Print o View) "Project Business Case".
Which artifacts in the Testing workstrean are created within the Realize Phase for the "New implemtation of SAP S/4 Hana Cloud" transition path? 2 answers Funtional Specifications Reporting Funtional Specification Funtional Test Scenarios User Acceptance Test-Plan .
Which artifacts are created within Application Design and Configuration workstream in the Explore phase of the "New implementation of SAP S/4hana transition path? 3 answers Detail Desing-Business Process Organization Structure Specification Data Requirement list- Register .
Which collaboration features can SAP Activate Jam users access? There are 2 correct answers to this question Update Key Deliverable wikis Tweet questions Ask questions Comment on documents. .
Which component of SAP Activate offers customers a reference solution in the cloud for a quick start? Please choose the correct answer Guided Configuration SAP Implementation Assistant SAP Activate Methodology SAP Best Practices. .
Which content is made available after you activate SAP Best Practices for a new financial implementation? There are 2 correct answers to this question Standard chart of accounts Pre-configured business processes Online help Implementation Guide. .
Which content packages are available in the SAP Package Library? There are 2 correct answers to this question SAP Activate Methodology SAP Best Practices Rapid Deployment Solutions Solution Builder. .
Which criterion does the Product Owner use to sequence the product backlog? Please choose the correct answer Resource availability Business priority Complexity Relative effort.
Which deliverable is specific to on-premise and NOT for the cloud? Please choose the correct answer Knowledge Transfer Adaptation Specification Learning Needs Analysis Technical Design Solution. .
Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning? Please choose the correct answer Detailed bottom-up effort estimate the breaks each user story up into hours or shorter tasks Relative estimate in ideal person days that reflects the best estimate provided by the project team Detailed bottom-up effort estimate by the SCRUM Master in story points based on the user story complexity Product Owner’s relative estimate of the effort that will be needed to implement the user story. .
Which end to end Application Lifecycle Management (ALM) solution can support you in managing requirements and software development for large, agile, innovation proyects? Please choose the right answer Change Request Managament Solution Manager Test Suite Focused Build Requeriment Management .
Which key activities does the Guided Configuration support you with? There are 3 correct answers to this question Create test data Test configured processes Train new users View solution scope Manage roles of configuration users.
Which key deliverable includes the development of RICEFW objects? Please choose the correct answer Custom Extensions Management Sprint Execution Enhancement Delivery Development Build. .
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer Navigate by Project Team Member Role Navigate by work stream Navigate by RACI matrix accountability Navigate by assigned Delivery Mode. .
Which new project roles are introduced with the SAP Activate Agile methodology? There are 2 correct SCRUM Master Design Thinking Coach Integration Lead Product Owner. .
Which of the following activities are part of the Deploy Phase of a Landscape Transformation journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question Solution Activation Access organizational and production readiness Training delivery Optimize software Change Control Management. .
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 3 correct answers to this question Sandbox system migration Custom code adjustment Development system migration Operations impact analysis Delta configuration.
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4 HANA Implementation? There are three correct answer Defining organizational structure Adjusting pre-delivered master data for workshops Creating sample transactional data for workshops Adjusting custom code objects Writing technical design documents.
Which of the following activities are performed in the Explore phase of SAP Activate in SAP S/4HANA Implementation? There are 3 correct answers to this question Organizational structure Adjusting custom code objects Creating transactional data Changing master data Implementing best practices.
Which of the following activities support the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question Value determination Data aging configuration Non-production systems migration Custom code Adjustment planning. .
Which of the following are available in the initial SAP Methodologies JAM Page? There are 2 correct answer Accelerators Task description Roadmaps Summary. .
Which ofthe following are examples of Ready-to-Run SAP S/4HANA system? 2 answer Sap Best Practice Explorer SAP Model Company Fully Activated Appliance SAP mission control center .
Which of the following are beneficits of using Ready To Use content? there are two answer Run SAP like a Factory Predectible Results Fast time to Value Minimun Totoal cost of ownership .
Which of the following are not phases of the SAP Activate methodology? There are 2 correct answers to this question Preparation Prepare Go-Live & Support Realize .
Which of the following are the benefits of SAP JAM? There are 2 correct answers to this question Easy to use Reduced Recovery Time Highly available User collaboration. .
Which of the following are the key responsibilities of the Scrum Master? There are 3 correct answers to this question Task initiator Responsible for the project delivery Leadership skill Team protection Team support. .
Which of the following are the pillars of SAP Activate? There are 3 correct answers to this question SAP Launch Methodology SAP Best Practices SAP Activate Methodology SAP ASAP Methodology Guided Configuration.
Which of the following building blocks are part of the SAP S/4HANA platform? There are 2 correct answers to this question LOB Cloud Solution SAP Fiori UX SAP HANA in-memory database SAP Solution Manager. .
Which of the following can be used to navigate through the roadmap? There are 2 correct answers to this question Phases Workstreams Steps Tasks .
Which of the following content best outlines the scope of the Integration Test? Please choose the correct answer a. Prototype b. Delta/gap solutions c. Data flows with non-SAP application" a. Solution baseline b. Delta/gap solutions c. Data flows with non-SAP application" a. Prototype b. Delta configuration c. Data flows between SAP solutions" a. Solution baseline b. Delta configuration c. Data flows between SAP solutions.".
Which of the following dimensions need to be considered during prioritization? Three are 3 correct.
Which of the following is a Key Deliverable of the Prepare phase? Please choose the correct answer Change Impact Analysis and Communication Plan Release and Sprint Plan Baseline Build Solution Scope and Value Determination. .
Which of the following is not a characteristic that the quality principles are based on? Please choose the correct answer Experience of Typical Pitfalls SAP Quality Award example winners Best Practices International standard. .
Which of the following is not correct about Fit/Gap Analysis? There are 2 correct answers to this question Minimize the needs for rework during realization. Validate pre-activate and pre-assembled solution in the development system. Prioritize delta requirement and gaps. Drive towards adopting customers processes. .
Which of the following is not correct about the REALIZE phase? There are 2 correct answers to this question The project team ensures that the build is meeting the business requirements. The team prepares for operations so that the functionality can be brought live. The beginning of the Realize phase the team prepares a list of all the requirements in a backlog Detailed design workshops are held. .
Which of the following is not correct about workstreams? There are 2 correct answers to this question It can span phases Workstreams are dependent on phase start and end. It is assigned as an attribute to phases, deliverables and tasks It is a collection of related deliverables .
Which of the following is true about a cloud implementation project? There are 2 correct answers The Starter System is specific to SAP S/4HANA Cloud. The entire transport system is kept intact and up and running. Starter Systems are not required to be in place for the 'Fit to Standard' workshops. In the prepare phase of a cloud implementation project the project team provide the customer with materials to review as self-enablement. .
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase? There are 3 correct answers to this question Design for the Gaps and Deltas Solution Scope and Value Determination Baseline Build Data Migration Approach Validation Workshops.
Which of the following SAP S/4HANA Landscape Transformation options are enabled? There are 3 correct answers to this question Security Migration Migration of Selected Applications Migration of Business Units System Consolidation System Upgrade.
Which of the following statement are the true regarding the SAP JAM site? Choose the correct It provides information only on cloud deployments. It provides information only on premise deployments. It provides information on both premise and cloud deployments. .
Which of the following statements about Scrum is correct? Please choose the correct answer In Scrum, as best practices, we have three main roles, and three artifacts or three ceremonies. The three ceremonies are sprint planning, daily scrum, sprint review (retrospective). Scrum Master defines and prioritizes features and gathers requirements. In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
Which of the following tasks are part of the Production support after the Go Live key deliverable? There are 2 correct answers to this question Resolve issues identified during the Hyper Care period Set up the Operations Control Center Perform a Technical systems test Provide further training to customer end users. .
Which of the following tasks are required in the Prepare Phase? There are 3 correct answers to this question Train the project team Identify relevant SAP Best Practices Approve the test strategy Set up the infrastructure to support the project Define the communication plan.
Which of the following tools are used for rapid database migration? There are 2 correct answers to this question SWPM (software provisioning manager) SAP Solution Manager Software Update Manager (SUM) Database Migration Option (DMO). .
Which of the following tools is used to install SAP S/4HANA. Please choose the correct answer SWPM (Software Provisioning Manager) Cloud Application Library SAP Solution Manager Data Migration server. .
Which of the following are components of SAP MODEL COMPANY? Three correct answer Business process Content for SAP Solution Manager Preconfigured Solution Bussines Driven Configuration Acceletarors Quality Gate Checklist .
Which of the following tools are specific to the Data Management Workstream? There are 3 SAP Solution Manager SAP Lanscape Trasnformation SAP Data Service SAP Roadmap Viewer SAP HANA Cockpit integration for both SAP S/4HANA Cloud and and SAP S/4HANA.
Which tool can you use to collaborate with other SAP Activate methodology practitioners? Please choose the correct answer SAP Implementation Assistant SAP Jam SAP Solution Manager Roadmap Viewer. .
Which tools does SAP Activate provide to support Guided Configuration? There are 3 correct answers to this question Model Company Self Service Configuration Solution Builder Expert Configuration SAP Solution Composer.
Which statement are part of the Golden Rules for SAP S/4 HANA Cloud Single Tenant Edition? There are two correct answer Foster Cloud principals and adherence to fit-to- standard approach Document Dereivation from golden rules for transparency and future use in upgrade Use Sap solution manager 7.2 with focuses buid Stick to the security standards of the custumer organization .
Why there is NOT Sandbox system en the "New Implementation" of SAP S/4HANA Cloud Single Tenant Editon transition path? Because the proyect team uses the DEV Sytem to confirm solution fit and define data requirement Because the SAP S/4HANA Cloud Single Tenant Edition contains predefined bussines processes which should NOT be changed Because the customer may use the SAP Model Company.
Who determines the priority of user stories in the backlog of an Agile project? Please choose the correct answer Project Team Project Manager SCRUM Master Product Owner. .
Who determines the tasks that are required to complete the committed backlog items in a sprint? Please choose the correct answer SCRUM Master Project Manager Project Team. Product Owner .
Working in Agile approach what should your planning look like at the begenning of the realice phase? Timeline of th Sprint may differ due to the workload Project Scope and Planning are complete and final User stories are in a Ready status for No more than the first three Sprint Go live scope is fixed on the fisrt of January, the following year .
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of selected key deliverables across the project phases? Please choose the correct answe a. Detailed system Assessment b. Production Readiness Check c. Code Adjustment d. Validation of Migration a. Detailed system Assessment b. Code Adjustment c. Validation of Migration d. Production Readiness Check a. Code adjustment b. Detailed System Assessment c. Production Readiness Check d. Validation of Migration a. Production Readiness Check b. Detailed system Assessment c. Code Adjustment d. Validation of Migration.
Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase? Please choose the correct answer a. Conduct Solution Validation workshops b. Set reference value c. Prioritize initial backlog d. Conduct Delta Design workshops a. Conduct Solution Validation workshops b. Conduct Delta Design workshops c. Set reference value d. Prioritize initial backlog a. Set reference value b. Conduct Solution Validation workshops c. Prioritize initial backlog d. Conduct Delta Design workshops a. Set reference value b. Prioritize initial backlog c. Conduct Delta Design workshops d. Conduct Solution Validation workshops.
What are transitions path to s/4HANA? System convertion New Implentation Selective Data Transition Database transition.
What can be found in the SAP Solution Implentation Roadmaps? there are three right answers Deliverables in each Phase Value Maps Detailed description of implentation task Accelerators to be used in the Project Library.
What can you do with Guided Configuration? there are 4 correct answers Initial configuration of you solution and recordinf of updates for continuos innovation Test you configured business processes System conversion Data migration Evaluete activated business processes and country versions.
There are several SAP options for creating data insights and providing summaries in a strucutured format for SAP customers, which of the following are part of the SAP Analytis and Reporting Portafolio? 4 options SAP Analytics Cloud SAPS/4 HANA Embedded Analytics SAP Process orchestration SAP Hybrid Solutions (BI/Planning/Predicitive SAP Analytics Hub.
I measures the expected value of you SAP initiatives with benchmaking surveys and bussiness case tools? chose the right answer Value Lifecycle Managment (VLM) SAP Transformation Navigator Enable Now Aplication Lifecycle Managment (ALM).
It is a software products which support content reuse across scenarios in-applications help and performance support, training simulation and test-script creation Value Lifecycle Managment (VLM) SAP Transformation Navigator Enable Now Aplication Lifecycle Managment (ALM).
Whitin the business Guide output, it provides capabilities, values drivers with aspiration Ranges and tracking KPIs Value Lifecycle Managment (VLM) SAP Transformation Navigator Enable Now Aplication Lifecycle Managment (ALM).
Custom Code Managment process in SAP Solution Manager provides which of the following capabilities? Define KPIs and report on CCM data Identify custom code and collect its usage statitics Perform static code checks integrate into ABAP Development Tools in Security Retire unused/obsolote custom code objects.
Which of the following adoption approaches are used in the ERP Implmentation Strategies? There are two rigth answers Big Ban adoption Passthrough adoption Phased adoption Exhaustive adoption.
What are the approaches for system Conversion to SAP S/A HANA? There are 3 answers to this cuestions Simplification Item Catalog approach Standard approach using Software Update Manager (SUM) Near-Zero Downtime technology (NZDT) approach Downtime-optimized conversion approach using Software Updates Manager (SUM).
The activities in the transitionpath of SAP S/4 HANA Cloud, Single-Tenant Edition (STE) and SAP CLoud are very similiar, what are the major differances? SAP S/4HANA Cloud STE is configures through IMG while SAP S/4HANA Cloud SSCUI'S SAP S/4HANA Cloud STE has longer relase cycles comparing to SAP/ S/4HANA Cloud SAP S/4HANA Cloud STE has shorter relase cycles comparing to SAP/ S/4HANA Cloud Different tools are used to manage Application Lifecycle of SAP S/4 HANA Cloud STE.
What ready-to-use system types are available in SAP Cloud Appliance Library? 3 answers Model Company Full Activated Appliance Trial Partner solution Application Lifecycle Managment.
What are the substream in Data Managment Workstream? 3 answers Data volumen managment Data aging Data migration Master data management Data legacy.
Which of the following is true about the Custumer Center of Experience (CCoE)? 3 Answers CCoE is only involved during the hypercare period in supporting business processes operations. CCoE´s mission is to provide transparency and efficiency of SAP implementacion, innovation, operation, and qualty of business processes and systems. CCoE is an organization model which server as collaboration hub across IT and LoBs. CCoE centrally drive continuos improvement continuos innovation.
What is the term used for workshop which are intended to sent value targets validate SAP Standard Functionally against custumer requirements and collect delta requirements n the "New Implementation" of SAP S/4HANA Transition Path? Solution Validation Desing Thinking Fit To Standard Delta Design.
What Solution Operation Framework can fulliment joint Business and IT organization, that will secury ransparency and effficiency of SAP implemetation, innovation,organization and quality of business processes and system? SAP Operations Control Center Custumer Center of Expertise Sap Activate Business TransformationManagment Methodology.
What Sprint Type are part of SAP ACTIVATE METODOLOGY? 3 answer Build Firm up Delay Initial Foundational.
What does the Content element of SAP Ativate Provide? There are three correct answers Business Precess Content Integration Content Migration Content End Users Guides.
Which of the following scenarios are availables for the "Selective Data Transition" Transition Path with the SAP LandScape Transition tool? There are 3 correct answer Security Migration System Update System Consolidation Extraccion of Business Units Comunication throught Data replication.
Where can you find Data Migration Template? SAP Roadmap viewer SAP S/4 HANA Migration Cockpit SAP Cloud Appliance Library SAP Best Practice Explorer.
Which of the following content best outline the sequence of the testing within the Application Design and Configuration in te REalize phase? 1. Sprint Test 2. User Acceptance Test 3. Integration Test 1.Sprint Test 2. Integration Test 3. User Aceptance Test 1. Integration Test 2. User Aceptance Test 3. Sprint Test.