1. With reference to organization assignments in Project Systems, which of the following statements are true? (More than one answer is correct) [2] Controlling area & Company Code assignments is mandatory at Project Definition level. Currency can be changed only if the controlling area does not allow different company code currencies. Business area assignment is mandatory at Project Definition level. Profit center assignment is mandatory at Project Definition level.
2. All the currency-dependent data in the Project System is managed in three different currencies in parallel. These are; (More than one answer is correct) [3] Bussines Area Currency Controlling Area Currency Object Currency Transaction Currency.
4. Workforce Planning in Project System, allows you to assign certain HR resources to activities of a project. Which of the following can be assigned? (More than one answer is correct) [3] Persons Organizational units Jobs Positions.
5. What are the pre-requisites for distributing work to HR Resources? (More than one answer is correct) [2] In Customizing for the Project System, you must have defined profiles for workforce planning in Resources. Assigned work centers to the internally processed activities. assigned one or more labor capacity to a work center.
6 With the reference to WBS scheduling, which of th following statements are FALSE? in WBS scheduling, the activities which are assigned to the selected WBS elements are scheduled. In networkscheduling on the other hand, all activities which belong to the network are scheduled. If you selected scheduling type "WBS determines date", the earliest start date of the activities is defaulted from the respective WBS elements in case of forward scheduling (or the latest finish date of the activities in case or backward scheduling). The execution of WBS scheduling consists of 2 steps: 1.Determining the initial dates (start dates for forward scheduling or finish dates for backward scheduling). 2.Transfering the dates of the activities into respective network headers and WBS elements. Activities which are not scheduled, but have relationships to activities involved in scheduling, are viewed as external activities. In this case, the dates of the external activity are taken into account as restricting dates.
7. Which of the following are possible user exits than can be used while processing materials from the Project Systems? (More than one answer is correct) [3] CNEX0009 -- EXIT_SAPLCOMK_001 CNEX0011 -- EXIT_SAPLCOMK_002 CNEX0015 -- EXIT_SAPLCN10_002 CN015AFZ -- EXIT_SAPLCNFZ_003.
8. With reference to material requirements in Project System (PS-MAT), which of the following statements are true? 9999 components may be created per network. Project System supports consignment stock. Component scrap is considered during BOM explosion.
9.Could a user with Access Control List (ACL) authorization "read" lock a project? YES NO.
3. Project System has it own Organizational structure, which can be a matrix structure. TRUE FALSE.