1. In SAP S/4HANA Project Systems, which of the following are used to represent materials required for a project? Please choose the correct answer. Response: Material Resources. Material Reservations. Material Requirements. Material Components.

2. How does SAP S/4HANA Project Systems support timely completion of project activities? Please choose the correct answer. Response: By integrating with time tracking tools. By sending alerts to the project manager. By automatically updating the project schedule. By comparing scheduled and baseline dates.

3. Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? There are 2 correct answers to this question. Response: An MRP group must be assigned. The materials must allow sales order or project stock. The exact lot size procedure must be used. The procurement type of the material must be internal.

4. How does SAP S/4HANA Project Systems ensure that projects generate the expected revenues? Please choose the correct answer. By automatically updating the revenue plan. By sending alerts to the finance team. By integrating with sales and distribution. By comparing planned and actual revenues.

5. Most of the reports in SAP Project System can be refreshed without exiting or closing the report. Which report must be restarted to update the displayed data? Please choose the correct answer. Individual Overviews. Hierarchical Reports. Structure Overview. Reports by Cost Element.

6. You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? There are 3 correct answers to this question. The duration is missing in the activity. The Determine Costs indicator in the network header rules out planned cost calculation. Integrated planning for the network is active. The activity output price for the activity type and cost center assigned to the work center is not maintained. The formula for costing in the work center is incorrect.

7. A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem? Please choose the correct answer. Response: Activate availability control for projects in the controlling area. Enter the plan data for each WBS element. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.

8. What is copied when transferring a simulation version back to an operative project? There are 3 correct answers to this question. Response: Maintenance orders assigned to the project. Actual work. Plan costs. Network activities. WBS elements.

9. You are using budgeting and active availability control. How can availability control be activated? There are 2 correct answers to this question. Response: Background activation (CJBV – Activate Availability Control). Automatic activation with assignment to an investment program. Automatic activation with budget assignment. Automatic activation with the first actual posting.

10. What are the prerequisites for resource-related billing? There are 2 correct answers to this question. Response: A header-account-assigned network that is assigned to a sales order item. Released WBS elements, activities, and/or activity elements. A dynamic item processor (DIP) profile with the appropriate settings. An activity-account-assigned network that is assigned to a sales order item.

11. How can you grant individual authorization for WBS elements and networks?. Set the system status to "Lock Master Data". Activate access control lists (ACL) for the project profile and the network profile. Define a user status to lock the business transaction Update Project. Activate access control lists (ACL) for the user master record.

12. What PP/DS master data is necessary for using PP/DS? There are 2 correct answers to this question. Response: Production version. Resource. Location. Material.

13. A project manager wants to view the status of all ongoing projects in a consolidated manner. Which feature in SAP S/4HANA would allow them to do this? Please choose the correct answer. Response: Project Overview Report. Resource Utilization Report. Cost Analysis Report. Milestone Trend Analysis.

14. The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements.What planning method for basic dates do you use? Please choose the correct answer. Free planning. Bottom-up. Top-down. Strict bottom-up.

15. Which of the following are benefits of effective reporting in SAP S/4HANA Project Systems? Please choose the correct answer. Real-time tracking of project revenues. Enhanced resource allocation based on reports. Improved decision-making based on insights. Simplified project planning.

16. In SAP S/4HANA Project Systems, which of the following are essential for scheduling and planning a project? Please choose the correct answer. Cost Dates. Planning Dates. Baseline Dates. Actual Dates.

17. What could be a reason to use expert mode in the valuation method for results analysis? Please choose the correct answer. Valuation in different currencies. Usage of different line IDs. Assignments of different accounts for postings to financial accounting. Billing WBS elements belonging to different company codes.

18. A company is planning to construct a new building. In SAP S/4HANA, how would the various stages like foundation, framing, and roofing be represented? Please choose the correct answer. As networks. As milestones. As WBS elements. As activities.

19. Where do you maintain the length of the project ID? Please choose the correct answer. Project profile. Special characters. Project type. Project coding mask.

20. In SAP S/4HANA, how are revenues that are expected but not yet realized represented?Please choose the correct answer. As realized revenues. As deferred revenues. As potential revenues. As forecasted revenues.

21. A company has completed a project for a client and wants to record the payment received. In SAP S/4HANA, how would this income be represented? Please choose the correct answer. As a cost element. As a revenue element. As a payment milestone. As a financial posting.

22. Which of the following processes in SAP S/4HANA Project Systems can provide inputs for generating accurate reports? Please choose the correct answer. Release of a work breakdown structure. Regular data validation and reconciliation. Posting of planned costs and revenues. Approval of a change request.

23. You used hierarchical revenue planning to plan revenues for WBS elements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this? Please choose the correct answer. The manual hierarchical revenue planning will be displayed only if expert mode is activated. Cost element reports can display costs but not revenues. The manual hierarchical revenue planning has no reference to cost elements. Cost element reports display integrated planning only.

24. In SAP S/4HANA, how are human resources that are allocated to a project represented? Please choose the correct answer. As cost elements. As work centers. As network activities. As material components.

25. In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning? Please choose the correct answer. Capacity planner group in the network header. Control key of an activity. Scheduling and distribution key. Scheduling and capacity category.

26. What is the primary purpose of baseline dates in SAP S/4HANA Project Systems? Please choose the correct answer. Cost Analysis. Resource Allocation. Project Reporting. Revenue Forecasting.

27. What is the primary purpose of using networks in SAP S/4HANA Project Systems? Please choose the correct answer. To define the scope of a project. To represent the chronological sequence of activities. To allocate budget for a project. To monitor the progress of a project.

28. Which sets of dates can be used to schedule networks? There are 2 correct answers to this question. Basic dates. Forecast dates. Baseline dates. Planned dates.

29. Which of the following statements about WBS elements in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. WBS elements represent individual tasks within a project. WBS elements can be used for budgeting and cost planning. Every WBS element requires a separate network. WBS elements can be further divided into activities.

30. Where can you assign the user status profile for WBS elements? There are 3 correct answers to this question. In the operative WBS element. In the project profile. In the project version. In the project definition of a standard WBS. In the project type.

31. You want to determine the planned costs for an internally processed activity. Which data do you need? There are 2 correct answers to this question. Activity type. Duration. Work. Profit center.

32. Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component? Please choose the correct answer. Set up the requirement date aligned with the activity start date and a negative offset of 5 days. Set up the requirement date aligned with the activity start date and an offset of 5 days. Set up the requirement date aligned with the activity finish date and an offset of 15 days. Set up the requirement date manually as February 5.

33. You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use? Please choose the correct answer. Easy Cost Planning (ECP) for WBS. Unit costing for WBS. Detailed planning for WBS. Planning of overall values.

34. Which of the following business processes do NOT lead to the booking of actual costs to an object? There are 2 correct answers to this question. Recording of external services in the service entry sheet. Goods receipt into valuated project stock. Goods receipt into unvaluated project stock. Goods receipt of a non-stock item.

35. Which of the following are benefits of effective reporting in SAP S/4HANA Project Systems? There are 3 correct answers to this question. A work center has not been assigned to the activity. The work center does not contain any available capacity data. The wrong activity type category is entered in the activity. The indicator that calculates capacity requirements is deactivated in the header of the network. The capacity distribution key field is empty.

36. Which of the following statements apply to project versions? There are 2 correct answers to this question. Project versions can be changed. Project versions are mandatory for Milestone Trend Analysis (MTA). Project versions can be created automatically based on user status. Manually created project versions always require a project version profile.

37. What is the primary purpose of cost planning in SAP S/4HANA Project Systems? Please choose the correct answer. To allocate funds for future projects. To ensure that projects are completed within budget. To monitor the profitability of a project. To generate financial statements for stakeholders.

38. Which of the following are benefits of integrating material management with SAP S/4HANA Project Systems? Please choose the correct answer. Real-time tracking of material consumption. Automatic generation of sales orders. Simplified resource planning. Enhanced financial reporting.

39. Where can you define a network as "header-account-assigned" or "activity-account-assigned"? Please choose the correct answer. Parameters for the network type. Project profile. Network profile. Network type.

40. Which of the following processes in SAP S/4HANA Project Systems can impact the planned dates of a project? Please choose the correct answer. Release of a work breakdown structure. Approval of a change request. Posting of actual costs. Completion of a network activity.

41. What is the primary purpose of baseline dates in SAP S/4HANA Project Systems? Please choose the correct answer. To determine the duration of a project activity. To compare the planned and actual progress of a project. To allocate resources based on availability dates. To set the target dates for project completion.

42. What are valid procurement types for stock items? Please select all the correct answers that apply. Preliminary purchase requisition for WBS element. Purchase requisition and Reservation for WBS element. Third-party order. Reservation for WBS element. Planned order.

43. You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message? Please choose the correct answer. Missing reservations for material components. Missing authorizations to release material components. Missing budget for material components. Missing material availability.

44. You want to use billing for a customer project. Which customizing object controls the billing of sales order items? Please choose the correct answer. Requirements class. Requirements type. Item category. Schedule line category.

45. You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? There are 2 correct answers to this question. If the reduction strategy isset in each activity. If the maximum reduction level is less than 100. If the appropriate reduction type is set in the parameters for network scheduling. If the reduction strategy is set in the network header.

46. Which of the following processes in SAP S/4HANA Project Systems can impact the planned resources of a project? Please choose the correct answer. Release of a work breakdown structure. Approval of a resource change request. Posting of actual resource costs. Completion of a network activity.

47. In SAP S/4HANA, how are costs that are directly attributable to a specific project activity represented? Please choose the correct answer. As direct costs. As indirect costs. As overhead costs. As allocated costs.

48. In SAP S/4HANA, how are dates that signify the actual start and finish of a project activity represented? Please choose the correct answer. Planning dates. Baseline dates. Forecast dates. Actual dates.

49. How can material components be assigned to network activities? There are 3 correct answers to this question. Using manual assignment. Using the bill of materials transfer. Using assigned sales orders. Using Project-Oriented Procurement (ProMan). Using the Internet-based catalog.

50. You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition? Please choose the correct answer. Enter 10 days as duration. Enter an offset of 10 days to the start date of the activity. Enter February 10 as fixed date. Enter an offset of -18 days to the finish date of the activity.

51. You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? There are 2 correct answers to this question. You can always maintain the actual start and finish date of a WBS element. You can always maintain the actual start if the WBS element has the status “Released” or “Partially released”. You can only maintain the actual start of a WBS element if the finish date is not maintained. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is “Released”.

52. You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? There are 2 correct answers to this question. Trigger automatic capacity leveling inside the project planning board. Shift activities backward or forward on the time axis where more capacities are available. Maintain subordinate internal activity elements assigned to other work centers. Increase the capacities of the work center in the project planning board.

53. A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? There are 2 correct answers to this question. Resource reports. Cost element reports. Structure information system reports. Hierarchical reports. Material reports.

54. In a case study where a company is implementing an IT infrastructure project, which of the following would be considered as resources in SAP S/4HANA? There are Three correct answers to this question. Servers and networking equipment. IT consultants and engineers. Project managers. Software licenses. Technical support team.

55. What business transactions can be used with Project-Oriented Procurement (ProMan)? There are 3 correct answers to this question. Generate purchase requisition. Stock transfer posting. Cancel goods issue. Confirm production order. Generate delivery.

56. Which statements describe planned and actual revenue for WBS elements? There are 2 correct answers to this question. Planned revenue can be transferred from a sales quotation. Actual revenue is posted via a billing document created from a sales order. Planned revenue requires a sales order assigned to a WBS element. Actual revenue is posted via a billing plan assigned to a WBS element.

57. Which object is used to allocate the costs from a claim to the project structure? Please choose the correct answer. Claim. Network activity. WBS element. Internal order.

58. Which of the following are benefits of effective revenue management in SAP S/4HANA Project Systems? Please choose the correct answer. Real-time tracking of project expenses. Enhanced resource allocation based on revenues. Improved cash flow management. Accurate forecasting of project profitability.

59. A company is rolling out a software update and wants to set a target date for completion. In SAP S/4HANA, how would this date be represented? Please choose the correct answer. As a milestone date. As a baseline date. As a planning finish date. As an actual finish date.

60. What is the reason for assigning billing plans in customer projects? Please choose the correct answer. Billing plans are copied automatically to the sales order item. Billing plans are used for revenue planning. Billing plans enable the billing process to be carried out. Billing plans are prerequisites for quotation creation.

61. You have created a network with successive activities. After scheduling the network, the Gantt chart shows that every activity has the same earliest start and earliest finish date as the network header. What could be the reason? Please choose the correct answer. The control key is set to no scheduling. The scheduling type is set to capacity requirements only. The normal duration of each activity is missing. There is a loop in the network.

62. In SAP S/4HANA Project Systems, which of the following is the highest-level object in the project hierarchy? Please choose the correct answer. Network. Project Definition. Activity. Milestone.

63. How can you record external service activities with service master data? There are 2 correct answers to this question. Confirm the network activity for external services. Confirm the activities in the Cross-Application Time Sheet (CATS). Post a goods receipt in the goods movement application (MIGO). Create a service entry sheet.

64. Which statement is valid regarding networks? There are 2 correct answers to this question. Relationships can be used to connect activities of different networks. Material components can be assigned to activity elements. A network activity can be assigned to several WBS elements. A network can be activity-account-assigned and header-account-assigned.

65. Which of the following actions can transfer actual costs for external processing? There are 2 correct answers to this question. Creating a purchase order. Approval of a service entry sheet. Posting a goods receipt. Approval of a goods receipt. Creating a service entry sheet.

66. What are some of the possible functions in user status profiles? There are 2 correct answers to this question. Restrict setting user status for individual users. Utilize priorities for setting the user status. Allow business processes forbidden by SAP system status. Ensure user status must always be set manually.

67. Which of the following data can be maintained in a standard network? There are 3 correct answers to this question. Material components. Basic dates for activities. Relationships. Document information records. Internally processed activities.

68. Which of the following are benefits of using WBS elements in SAP S/4HANA Project Systems? Please choose the correct answer. Simplified project planning. Enhanced resource allocation. Real-time tracking of project progress. Improved stakeholder communication.

69. Which of the following statements about resource planning in SAP S/4HANA Project Systems are true? Please choose the correct answer. Resources can be planned at the network activity level. Resource planning is automatically updated based on project progress. Work centers represent both human and machine resources. Resources can only be non-stock items.

70. You are working with networks and WBS elements. Which of the following statements applies? Please choose the correct answer. You have to activate the operative indicator Account Assignment Element for WBS elements with activities. You have to maintain a network profile in the project profile. You can reassign an activity from one network to another. You can assign the network header to multiple WBS elements.

71. Which objects can be used to specify settlement rules?. WBS elements. Network header for activity-account-assigned networks. Standard WBS elements. Network activity for activity-account-assigned networks. Project definition.

72. You have assigned a material to a network activity and want to determine the requirement date related to this activity. What set of dates do you have to maintain? Please choose the correct answer. Basic dates of the WBS. Forecast dates of the WBS. Basic dates of the network activity. Actual dates of the network activity.

73. You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget? Please choose the correct answer. Easy Cost Planning. Availability control. Cost forecast. Results analysis.

74. Which of the following is visible in the project planning board? There are 2 correct Answers to this question. Capacity requirements. Maintenance orders assigned to an activity. Project-relevant purchase orders. Production orders assigned to WBS elements.

75. Which planning method can prevent further rescheduling of activities? Please choose the correct answer. Workforce planning. Capacity leveling. Partial confirmation of activities. Capacity requirements activation.

76. How can you search in the structure overview based on the user status? There are 2 correct answers to this question. By searching for the individua lstatus. By searching for the status profile. By searching via status selection profile. By searching via status combination code.

77. You want to extrapolate basic dates from lower to higher-level WBS elements. The duration of higher-level elements should NOT be reduced. Which planning method do you choose? Please choose the correct answer. Bottom-up. Strict bottom-up. Free planning. Top-down.

78. In SAP S/4HANA, how can a project manager ensure that the reports generated are accurate and up-to-date? Please choose the correct answer. By integrating with external reporting tools. By regularly updating the project plan. By ensuring data consistency across modules. By setting up automatic report generation.

79. You want to confirm working hours to a WBS element using SAP Cross Application Time Sheet (SAP CATS). However, once you enter the WBS element and the working hours in SAP CATS you receive an error message. What could be the reason? Please choose the correct answer. The system status "created" is active. The system status "master data locked" is active. You are not the responsible person for that WBS element. The confirmation exceeds the budget assigned to the WBS element.

80. A company is planning a project and wants to allocate human resources and machinery. In SAP S/4HANA, how would these allocations be represented? Please choose the correct answer. As cost elements. As work centers. As network activities. As WBS elements.

81. You want to assign milestones to WBS elements. For what can you use these milestones? There are 2 correct answers to this question. To start workflow tasks. For trend analysis. To transfer the actual date to the billing plan. To set an actual finish date for WBS elements.

82. You want to maintain basic data and dates of a WBS element on the same tab. Also, basic start and basic finish should be mandatory fields. What do you need to configure? There are 2 correct answers to this question. Define Layout Detail Screen for the WBS element to specify customer-specific tabs. Define Create User-Defined Fields for the WBS element to specify the mandatory fields. Define Field Selection for the WBS element to specify the mandatory fields. Define Table Settings for the WBS element to specify customer-specific tabs.

83. Float time is calculated during scheduling. Which of the following statements about float time are correct? There are 3 correct answers to this question. The maximum size of a free float is as large as the total float of an activity. Float time can be negative. By default, critical activities have a float time, which is less than or equal to zero. Activities with the time constraint "Must start on" always have a negative float time. The float time of WBS elements is calculated by extrapolation.

84. What are the prerequisites for delivering materials from the project? There are 2 correct answers to this question. A shipping point is necessary. A sales order must be created in advance. A sold to party is necessary. A delivery document type must be configured.

85. Which objects do you have to maintain to enable automatic assignment of material components to the project? There are 2 correct answers to this question. WBS element. BOM item. Material master. Network activity.

86. Which of the following factors influence the scheduling of internal processing activities? There are 3 correct answers to this question. Whether the work for the internal activity is greater than its duration. The factory calendar in the work center used for the internal processing activity. The relationships between activity elements. An activated Scheduling indicator in the control key of the internal processing activity. The unit (for example, hour, day) of the field Normal Duration field of the activity.

87. You have implemented automatic requirements grouping for projects. Once you check the materials cabin and fork you realize that the requirements are grouped for cabin but not for fork. What might be the reason? Please choose the correct answer. The grouping indicator of the top WBS element is set to a single MRP Group. The network is set to no grouping for specific MRP Groups. The MRP Group for fork is deactivated for grouping. The project definition is set to no project stock.

88. Which of the following statements about reporting in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. Reports can provide real-time data on project progress. Reporting is only possible at the end of a project. Custom reports can be created to cater to specific needs. Reports can only be generated by the finance team.

89. How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question. By searching for the individual status. By searching for the status profile. By searching via status selection profile. By searching via status combination code.

90. What is the primary purpose of revenue planning in SAP S/4HANA Project Systems? Please choose the correct answer. To forecast the potential income from future projects. To ensure that projects are profitable. To allocate budget based on expected revenues. To generate financial statements for stakeholders.

91. How can you update the degree of processing for an activity? Please choose the correct answer. By using results analysis. By scheduling the activity. By confirming the activity. By changing the activity.

92. When you create a service activity in your network, what data can be entered? There are 3 correct answers to this question. Service specification. Material master within service specification. Vendor. Service purchase order number. Overall limit (maximum value of all unplanned services).

93. When using budgeting and active availability control, which business transactions affect the current budget? There are 3 correct answers to this question. Cost element planning. Original budget. Revenues. Transfers. Supplements.

94. You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item? Please choose the correct answer. The person responsible for the work center. The person responsible for the network activity. The MRP controller for the network. The person responsible for the superior WBS element.

95. You are working with predefined project coding masks to create projects. Which of the following statements apply? There are 2 correct answers to this question. You can use an indicator to determine that only coded project numbers may be used within SAP Project System. You can only use numbers for a project coding mask definition. You can use the same coding mask forstandard projects and operative projects. You can shorten the project mask even when there are existing projects.

96. You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates? Please choose the correct answer. Milestone. Activity. Activity element. Network header.

97. How can you confirm the working hours of different work centers for a single activity? Please choose the correct answer. Enter direct activity allocation assigning multiple work centers. Assign multiple work centersto the activity. Enter multiple work centers within a single confirmation. Create multiple confirmations for the activity and use the appropriate work center for each confirmation.

99. Which of the following processes in SAP S/4HANA Project Systems triggers the creation of a new WBS element? Please choose the correct answer. Approval of a project budget. Completion of a preceding WBS element. Identification of a new task within a project. Release of a network activity.

100. Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend? Please choose the correct answer. Capacity load work center view. Individual overview capacity requirements. Structure overview. Extended capacity evaluation. None.

101. Which of the following apply to dynamic item processor (DIP)? There are 3 correct answers to this question. Sales prices are maintained in the DIP profile. Usage of cost elements is mandatory. Sources can be based on line items. DIP is used to create a quotation. Material determination is mandatory.

102. In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario? Please choose the correct answer. The purchase order is updated automatically to match the new quantity while saving the project. A workflow can be triggered to inform the purchasing group. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO). The system automatically creates a new purchase requisition with the difference to the original quantity.

103. In a case study where a company is offering cloud solutions, which of the following would be considered as sources of revenue in SAP S/4HANA? Please select all the correct answers that apply. Subscription fees. Setup and installation charges. Data storage costs. Customization services. Technical support subscriptions.

104. In a scenario where a company is launching a new product, which of the following would be considered as WBS elements in SAP S/4HANA? Please select all the correct answers that apply. Product design. Market research. Manufacturing. Distribution. Sales and marketing.

105. How does SAP S/4HANA Project Systems ensure that stakeholders are informed about the progress and status of projects? Please choose the correct answer. By sending automated email notifications. By generating and sharing regular reports. By integrating with communication tools. By updating the project dashboard in real-time.

106. Which of the following statements about material planning in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. Material components can be assigned to network activities. Every material component requires a separate purchase order. Material availability check can be performed for network activities. Material components can only be non-stock items.

107. Which sales documents can update planned revenues on WBS elements? There are 2 correct answers to this question. Sales order. Billing. Inquiry. Quotation.

108. In SAP S/4HANA Project Systems, which functionality is primarily used to plan and record the income generated from a project? Please choose the correct answer. Cost Planning. Revenue Planning. Payment Scheduling. Budget Allocation.

109. In SAP S/4HANA, how are human resources that are allocated to a project represented? Please choose the correct answer. To allocate funds for resource procurement. To ensure that resources are utilized efficiently. To monitor the cost of resources used in projects. To generate resource-related reports for stakeholders.

110. A company is constructing a bridge and needs to procure steel beams. In SAP S/4HANA, how would this requirement be represented? Please choose the correct answer. As a network activity. As a milestone. As a material component. As a work breakdown structure.

111. You want to use subnetworks during the project. Which of the following statements describes subnetworks? Please choose the correct answer. Maintenance orders can be defined as subnetworks. The scheduling type of a subnetwork is always copied from the superior network. A subnetwork cannot be defined for a superior subnetwork. Subnetworks must be scheduled separately from the superior network.

112. A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Please select all the correct answers that apply. A procurement indicator must be assigned to the activity. The material master of the component must permit project stock management. The network is assigned to a sales order item. The network activity is assigned to a WBS element. The Project Stock indicator is set in the project definition (non-valuated or valuated).

113. Which of the following processes in SAP S/4HANA Project Systems can impact the planned costs of a project? Please choose the correct answer. Release of a work breakdown structure. Approval of a change request. Posting of actual revenues. Completion of a network activity.

114. How does SAP S/4HANA Project Systems ensure that materials are available when required for a project activity? Please choose the correct answer. By generating automatic purchase requisitions. By reserving stock materials in advance. By sending alerts to the project manager. By integrating with supplier management systems.

115. You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? There are 2 correct answers to this question. The material master is set to external procurement. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never". The availability check for material components indicates missing parts. The material is assigned to the activity as a non-stock material.

116. What is the primary purpose of material reservations in SAP S/4HANA Project Systems? Please choose the correct answer. To reserve stock materials for future use in projects. To track the cost of materials used in projects. To generate purchase requisitions for non-stock materials. To determine the bill of materials for a project.

117. Which of the following statements about revenue planning in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. Revenues can be planned at both WBS and network activity levels. Revenue planning is automatically updated based on project progress. Revenue elements represent the different types of income in a project. Revenues can only be planned for completed projects.

118. Which of the following are benefits of effective resource management in SAP S/4HANA Project Systems? Please choose the correct answer. Real-time tracking of resource costs. Improved project scheduling. Enhanced resource allocation and utilization. Simplified financial reporting.

119. How are earliest dates and latest dates of activities scheduled? Please choose the correct answer. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling. Earliest dates and latest dates are scheduled by forward scheduling. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.

120. Which of the following processes in SAP S/4HANA Project Systems triggers a requirement for materials? Please choose the correct answer. Release of a work breakdown structure. Release of a network activity. Completion of a milestone. Approval of a project budget.

121. In SAP S/4HANA Project Systems, which of the following are used to monitor and control the costs of a project? Please choose the correct answer. Cost Elements. Cost Centers. Cost Indicators. Cost Plans.

122. Which object is relevant in assembly processing to create an assembly order for the SD document? Please choose the correct answer. Item category. Requirement class. Control key. Project profile.

123. In a scenario where a manufacturing company is producing a new line of electronics, which of the following would be considered as material components in SAP S/4HANA? There are 3 correct answers to this question. Microprocessors. Display screens. Assembly line workers. Plastic casings. Marketing campaigns.

124. Which of the following are benefits of effective date management in SAP S/4HANA Project Systems? Please choose the correct answer. Real-time tracking of project costs. Enhanced resource allocation. Simplified financial reporting. Improved project scheduling and planning.

125. Which of the following statements about cost planning in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. Costs can be planned at both WBS and network activity levels. Cost planning is automatically updated based on project progress. Cost elements represent the different types of costs incurred in a project. Costs can only be planned for completed projects.

126. What is the primary purpose of reporting in SAP S/4HANA Project Systems? Please choose the correct answer. To provide insights for future project planning. To ensure that projects are completed within budget. To generate financial statements for stakeholders. To monitor and control the progress of projects.

127. Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget? Please choose the correct answer. Structure overview for budgets. Cost element report on budget updates. Hierarchical report on budget updates. Line item report for budgets.

128. Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? There are 2 correct answers to this question. Sales order items. Purchase order items. Reservations. Internal orders.

129. Which organizational structures are required for network activities? There are 3 correct answers to this question. Company code. Sales organization. Plant. Controlling area. Operating concern.

130. A company is undertaking a project and wants to allocate costs for labor, machinery, and materials. In SAP S/4HANA, how would these costs be categorized? Please choose the correct answer. As cost indicators. As cost elements. As cost allocations. As cost centers.

131. Which of the following statements about resource planning in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. Resources can be planned at the network activity level. Resource planning is automatically updated based on project progress. Work centers represent both human and machine resources. Resources can only be non-stock items.

132. In SAP S/4HANA, how are materials that are directly used in a project and not stored in stock represented? Please choose the correct answer. Stock materials. Non-stock materials. Consumable materials. Reserved materials.

133. An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates? Please choose the correct answer. The control key. The scheduling parametersfor the network. The network profile. The table of MRP controllers.

134. What functions are available for period end closing in SAP Project System? There are 3 correct answers to this question. Milestone trend analysis. Progress analysis. Confirmations. Settlement. Results analysis.

135. How does SAP S/4HANA Project Systems support adherence to planned durations for WBS elements? Please choose the correct answer. By sending alerts to the project manager. By automatically updating the project schedule. By integrating with time tracking tools. By comparing planned and actual dates.

136. Which of the following statements about date types in SAP S/4HANA Project Systems are true? There are 2 correct answers to this question. Baseline dates are used for comparison with actual dates. Planning dates are automatically updated based on project progress. Actual dates represent the planned start and finish of an activity. Milestone dates signify important events in a project.

137. Which report can use user-specific layouts? Please choose the correct answer. Enhanced individual overview. Hierarchical report. Line item report. Cost element report.

138. To which object can you assign a factory calendar? Please choose the correct answer. Milestone. Network header. Material component. Relationship.

139. You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use? Please choose the correct answer. Project profile. Network profile. Data entry profile. Network type.

140. The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element? Please choose the correct answer. Calculation of actual values. Creation of purchase orders. Activity allocation. Goods receipt for purchase orders.

141. Where do you control whether a project stock is managed as valuated or non-valuated project stock? Please choose the correct answer. In the network activity. In the WBS element. In the material master. In the project definition.

142. A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use? Please choose the correct answer. Only capacity requirements. Forward. Current date. Backward.

143. You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents? Please choose the correct answer. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> Invoice receipt. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt.

144. In SAP S/4HANA, how are tasks that are dependent on each other represented within a project? Please choose the correct answer. As independent WBS elements. As milestones. As linked activities within a network. As separate networks.

145. In a case study where a company is organizing a global conference, which of the following would be considered as WBS elements in SAP S/4HANA? Please select all the correct answers that apply. Venue selection. Speaker invitations. Marketing and promotions. Ticket sales. Post-event feedback collection.

146. In SAP S/4HANA Project Systems, which of the following are considered resources? There are 2 correct answers to this question. Cost Elements. Work Centers. Material Components.

147. Which of the following processes in SAP S/4HANA Project Systems can impact the planned revenues of a project? Please choose the correct answer. Release of a work breakdown structure. Approval of a change request. Posting of actual costs. Completion of a network activity.

148. For which objects can billing plans be created? There are 2 correct answers to this question. Sales order items. Milestones. Project definition. WBS elements.

149. Which of the following are benefits of effective cost management in SAP S/4HANA Project Systems? Please choose the correct answer. Real-time tracking of project revenues. Enhanced resource allocation. Improved cash flow management. Accurate project budgeting and forecasting.

150. You have created a network with planned work for internal activities. In a capacity planning report, you discover that no capacity requirements were determined. What are the possible reasons for this? There are 3 correct answers to this question. A work center has not been assigned to the activity. The work center does not contain any available capacity data. The wrong activity type category is entered in the activity. The indicator that calculates capacity requirements is deactivated in the header of the network. The capacity distribution key field is empty.

151. You want to allocate overhead rates to a WBS element. What must you assign to the WBS element? Please choose the correct answer. Investment profile. Settlement rule. Results analysis key. Costing sheet.

152. In SAP S/4HANA Project Systems, which functionality provides insights into the progress, costs, and revenues of a project? Please choose the correct answer. Cost Analysis. Resource Allocation. Project Reporting. Revenue Forecasting.

153. What is the primary purpose of resource planning in SAP S/4HANA Project Systems? Please choose the correct answer. To allocate funds for resource procurement. To ensure that resources are utilized efficiently. To monitor the cost of resources used in projects. To generate resource-related reports for stakeholders.

154. How does SAP S/4HANA Project Systems ensure that resources are allocated and utilized efficiently in a project? Please choose the correct answer. By sending alerts to the project manager. By automatically updating the resource plan. By integrating with resource scheduling tools. By comparing planned and actual resource usage.

155. What functionality can you perform with activity elements? Please choose the correct answer. Create relationships. Assign work centers and capacities. Schedule WBS elements. Assign material.

156. How does SAP S/4HANA Project Systems ensure that projects are completed within the allocated budget? Please choose the correct answer. By sending alerts to the finance team. By automatically updating the cost plan. By integrating with financial accounting. By comparing planned and actual costs.

157.Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events. What is the requisites for implement scheduling of events?. A. Priority of events must be set. B. Scheduling parameters for material scheduling must be set. C. Events must be released manually. D. Event scenarios must be defined.

158.You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that? Note: there are 2 correct answers for this question. A. Use an offset of two days for the relationship of both activities. B. Use an offset of two days for milestone date. C. Use an offset of two days for the requirement date of the material component. D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.

159.Your customer wants to plans and post revenues for WBS elements. What is crucial for the implementation of revenues planning and posting for WBS elements?. A. At least one WBS element must be a billing element. B. The indicator "Project type" must be set to "Customer project". C. Revenue planning and billing must be activated in the corresponding network type. D. A sales order item has to be assigned to each WBS element used for revenue planning.

160. You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project. What are the prerequisites? Note: There are 3 correct answers to this question. A. A bill of material with sales views. B. A material master with sales views. C. Assignment between material and standard network. D. Standard network with activities. E. A production order.

161. Your customer use a tight integration between sales order and WBS with network to deliver finished and semi-finish product. What benefit do they have when using delivery from project (CNSO)?. A. With delivery from projects You can generate goods issues for project without creating delivery documents. B. With delivery from projects good receipt are automatically posted while saving. C. With delivery from projects you can generate purchase requisitions for sub-contractors. D. With the delivery from project you can deliver material component assigned to your network.

162. Which the following statement regarding networks are correct? Note: there are 3 correct answers for this question. A. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center. B. You can assign more than one activity element to a network activity. C. Capacity requirements of a network activity are reduced when the activity is confirmed. D. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity. E. You can assign the same work center to more than one activity on the same network.

163. You plan double the work on each internal activity for multiple project. What do you recommend?. A. Use mass change (CNMASS) in the project system. B. Double the work of each internal activity, one after another, in the project Builder. C. Double the capacity in the work center. D. Use mass change within the project Builder (CJ20N).

164. You want to exchange data between SAP Project System and Microsoft What interface do you use?. A. The EPS interface (External Project Software). B. No interface to Microsoft Project is available. C. The catalog interface. D. you do not need and interface. You can exchange data using object link.

165. Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question. A. You can map a project using only one WBS or one network. B. You can also represent a project using a WBS and one or more networks. C. You can create a project based on a Activity. D. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.

166. A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?. A. Settlement rules. B. Costing Sheet. C. Investment profile. D. Results analysis key.

167. You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?. A. The field key is the default value for the WBS element and the activities too. B. The tab user fields is invisible. C. The field key is hard coded in the WBS element. D. The field key is the default value only for the WBS element.

168. The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer. A. Plant. B. Controlling area. C. Company code. D. Planning department.

169. You intent to work with predefined project coding mask to create project definitions. What do you have to consider?. A. You can create project coding mask X... event if there are project numbers beginning with X. B. The standard project definition must differ from the definition of the operative project. C. You can use only numbers for a project coding mask definition. D. You can use an indicator to determine that only coded project numbers may be used within the project system.

170. Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question. A. Schedule Manager. B. Project Builder. C. Project planning board. D. Easy Cost Planning.

171. You Want assign milestone to WBS element? For what can you use these milestone. A. To create standard network. B. To start workflow task. C. For trend analysis. D. To set an actual finish date for WBS element-.

172. How can the system activate requirements (such as reservations or purchase requisitions)? Note: There are 2 correct answers to this question. A. Immediately, by saving the project. B. Automatically, using the requirement date and the replenishment lead time. C. Using a standard milestone activity. D. When releasing a network or an activity.

173. How are capacity requirements determined?. A. Independent of scheduling and according to the capacity planner group. B. Using scheduling and the capacity category. C. Using the control key of an activity. D. Using scheduling and distribution key.

174. Which statement regarding the creation of a new work breakdown structure (WBS element) are true? Note: there are 3 correct answer for this question. A. You can create several WBS elements per level. B. A new work breakdown structure must contain up to 10 levels. C. A WBS element of the new project can be assigned to a different project definition. D. WBS element can be a planning element, an account assignment element, and a billing element at the same time. E. The WBS structure can contain several level 1 WBS element.

175. A customer use cross- company - code project with a top billing element and additional billing element underneath for each company code. Although the internal .. correctly the result analysis summarizes all values to the highest billing element. How can they split the results to the different company codes?. A. Settle the WBS element to the highest billing element before you do the result analysis. B. Split the project intdifferent project according to each company code. C. Change the project structure so that it correspond better to the company's organization structure. D. Adjust the customizing of the valuation method in the expert mode of the periodic results analysis accordingly.

176.Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates. What standard report do you recommend?. A. Structure overviews for budget. B. Cost element report on budget updates. C. Line item report for budget. D. Hierarchical report on budget updates.

177.You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order. What do you have to consider?. A. The maintenance orders must be assigned to WBS element. B. The maintenance order s must be assigned to the same budget profile as the project definition. C. The maintenance orders must be assigned as sub-networks. D. The maintenance orders must be assigned to the same plant as the network.

178. You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason? Note: there are 2 correct answers for this question. A. The procurement type in the material master is set to in-house Production. B. The item category of the materials is set to stock item. C. The material has no material number. D. The item category of the materials is set to non-stock item.

179. Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board. Note: there are 3 correct answers for this question. A. Display of production orders assigned to WBS element. B. Display of plant maintenance orders for activities. C. Display of project cost plan. D. Display of project -relevant purchase order. E. Using specific color management for Gantt Chart.

180. Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled. Which set of dates can be used for scheduled for network? Note: there are 2 correct answer for this question. A. Planned dates. B. Fundamental dates. C. Basic dates. D. Baseline dates. E. Forecast dates.

181. You are using network and internal activities in your project. You have already create a purchase requisition and the bid invitation and have entered the quotation ... What is the typical sequence for the following business transactions and document. A. Benefic check - Acceptance of performed service- vendor selection - purchase order handing purchase order monitoring-Good receipt - invoce .. B. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check-Acceptance of performed services. C. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt. D. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt-Invoice receipt.

182. A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost, they do not want to produce..Which setup do you recommend?. A. Assign a sales order to a project with appropriate hierarchy levels. B. Assign a network to a sales order. C. Assign Several production orders to a sales order. D. Assign One production order to a sales order.

183. How can you define external task in your project? Note: there are 2 correct answers for this question. A. Assign a purchase order for external processing to the project definition. B. Create an external activity in a network. C. Create a service milestone. D. Create a service activity in a network.

184. What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question. A. Project simulations allow posting of actual data. B. Project simulations can be created without using an operational project as a template. C. Project simulations can be used to plan structures and costs. D. Project simulations can create purchase requisitions. E. Multiple project simulations can be used simultaneously.

185. The various work packages in the project are described as individual______________. Choose the correct answer. A. WBS elements. B. Project definitions. C. Tasks. D. Activities.

186. The individual tasks in the project are mapped as activities in a WBS. Determine whether this statement is true or false. True. False.

187. Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question. A. Saving a supplier invoice. B. Saving a service entry sheet. C. Saving a goods receipt. D. Saving a purchase order.

188. You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder? Note: there are 3 correct answers for this question. A. Project milestone. B. Standard network. C. Standard Project definition. D. Project version. E. Project definition.

189. 109.What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question. A. Confirm production order. B. Post Goods Issue. C. Generate purchase requisition. D. Generate delivery. E. Cancel goods issue.

190. You work with Project Builder, CJ20N, and want to use standard templates in your project structure. Which standard templates can you use. There 1 correct option. Standard Milestones. Standard Time Scheduling. Standard BOM. Standard Cost Planning.

191. You want to use billing for customer project, you can assign the billing plan to a WBS Element or to a sales order item. What is the reason for assigning billing plans in customer projects?. The billing plan can be carried out with a billing plan for a WBS element. Billing plans for WBS elements are copied automatically to the sales order item. Billing plans for WBS elements are prerequisites for quotation creation. Billing plans for WBS elements are used for revenue planning.

192. In your project you choose internal activities to confirm actual dates. After you partially confirmed an internal activity, you want that the actual start will be considered for the calculation of the earliest scheduled dates. How can you implement this?. Deactivate actual date consider indicator in Parameters for Network Scheduling. Activate the shift order indicator in Parameters for Network Scheduling. Deactivate the shift order indicator in Parameters for Network Scheduling. Activate actual date consider indicator in Parameters for Network Scheduling.

193. You plan to work with Networks and WBS elements structures, What do you have to consider?. You can reassign an activity from one network to another. You have to maintain a network profile in the project profile. You can assign the network header to multiple WBS elements. You have to activate the operative indicator Account Assignment Element for WBS elements withactivities.

194. You use networks and internal activities in your project. You have activated capacity requirements andnotice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? There are 2 correct answers to this question. Create subordinate internal activities elements assigned to other work centers. Capacity leveling is done automatically after scheduling and saving. Shift activities backward or forward on the time exist where more capacities are available. In crease the capacities of the work center in the Project Planning Board.

195. You use overall revenue planning CJ42 to plan revenue for WBS elements. A colleague claims that the cost element report for planned r evenie doesn`t show any revenue at all. Why does the cost element report not show up any revenue?. Cost element report display integrated planning only. The overall revenue planning has no reference to cost elements. Cost element reports can display costs but not revenues. The overall revenue planning will be displayed only if expert mode is activated.

196. Whan can you plan using internal activities?. Material procurement for a production order. Workforce planning. Multiple work centers on one internal activity. Resource-related budgets.

197. The Engineering work center is assigned to internal activity "Drawings". The activity is released as you want to confirm hours for the work centers "Design", "Mechanics" and "Quality Inspection". How can you confirm the woking hours for differents work centers to a singles activity?. Create multiple confirmations for the activity Drawings and use the apropiate work center for each confirmation. Assing multiple work centers to the activity Design. Enter multiple work centers within a single confirmation. You cannot confirm working hours of a different work centers to a singles activity.

198. Which statements about Networks are true?. Relationships can be used to connect activities of different networks. A network activity can be assigned to several WBS elements. A network can be activity-account-assigned and header-account-assigned. Material components can be assigned to activity elements.

199. Your project consists of WBS elements, several networks and subnetworks. What are the advantages for new overall network scheduling CN24N instead of the old overall network scheduling CN24?. Detailed subnetwork monitor. Introduction of a configurable level concept for the targeted selection of subnetworks. Scheduling that takes available capacity and material availability into account. Improve performance throught the targeted selection of subnetworks to be scheduled. Scheduling of subnetworks and subordinate internal orders.

200. Can the user status forbid business transactions that the system status allows?. Yes if the status number of the user status is defined with higher priority. No system status has a higher priority than user status. No user status can only create a warning. Yes by creating an appropiate status profile.

201. You want to extrapolate basic dates from lower to higher-level WBS elements. Which planning method do you choose?. Strict bottom-up. Bottom-up. Top down. Free planning.

202. Your customer has created networks with internal activities and generated capacity requirements. Now they want to analyze tha capacity of their project. Which report do you recommend. Extended capacity evaluation CM50. Capacity load work center view CM01. Individual overview capacity requirements CN50N. Structure overview CN41.

203. Your customer wants to make sure that a certain tusk must start on a given date. Where can you mantain constraints limits for starts dates?. Milestones. Activity Elements. Network Header. Activity.

204. You want to plan costs. Therefore you have defined a costing variant and a valuation variant for your network. Which of the following objects can be calculated via the network valuation variant?. Documents assigned to activities. Internally processed Activites. Externally processed Activites. WBS Elements. Material components assigned to activities.

205. A customer wants to use project simulations in the quotation phase. What project simulations characteristics do you highlight?. Project simulations allows posting actual data. Multiple project simulations can be used simultaneously. Project simulations can create purchase requisitions. Project simulations can be created without using an operational project as a template. Project simulations can be used to planned structure and costs.

206. Your customer wants to use milestone billing. Billing elements are implemented. What do you have to do in addtion to enable milestone billing?. Create a billing plan assigned to a WBS element. Activate indicator sales document date for milestones. Set up percentage of completetion for milestones. Activate milestones functions. Create a billing plan assgned to a sales order item.