Which new project roles are introduced with the SAP Activate Methodology for the Agile delivery approach? There are 2 correct answers to this question. Product Owner Integration Lead Design Thinking Coach SCRUM Master.
Which of the following activities are part of the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 3 correct answers to this question. Development system migration Delta configuration Sandbox system migration Custom code adjustment Operations impact analysis.
In which phase should you first run the SAP Readiness Check for SAP S/4HANA in a "Selective Data Transition" transition path, in a System Consolidation scenario that includes conversion from SAP ERP? Please choose the correct answer. Discover Prepare Realize Explore.
Which of the following scenarios are enabled for the "Selective Data Transition" transition path with the SAP Landscape Transformation tool? There are 3 correct answers to this question. Extraction of Business Units System Upgrade Security Migration Consolidation through online data replication System Consolidation.
What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices? Please choose the correct answer. Apply SAP Best Practices with the Configure your Solution application Activate and apply SAP Best Practices with SAP Solution Manager Activate and apply SAP Best Practices content with the self-service configuration UI Assemble and apply SAP Best Practices to the system.
Which estimation technique can be used in to size the User Stories during Sprint Planning? Please choose the correct answer. Detailed bottom-up effort estimate by the Scrum Master in Story Points based on the User Story complexity Detailed bottom-up effort estimate that breaks each User Story up into hours or shorter tasks Relative estimate in Ideal Person Days that reflects the best estimate provided by the project team Product Owner's relative estimate of the effort that will be needed to implement the User Story.
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? There are 2 correct answers to this question. Always Connected Run SAP Like a Factory Intelligent Enterprise Build SAP Like a Factory.
Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new implementations? There are 3 correct answers to this question. Value Determination Production Support Plan Value Audits Change Management Plan Scope Validation.
Which Value Chains does SAP Solution Manager 7.2 deliver? There are 3 correct answers to this question. Cash-to-Order Detect-to-Correct Requirements-to-Deploy Request-to-Fulfill Hire-to Retire.
Which of the following tasks are part of the Production support after the Go Live key deliverable? There are 2 correct answers to this question. Perform a Technical systems test Resolve issues identified during the Hyper Care period Set up the Operations Control Center Provide further training to customer end users.
Which key deliverable includes the development of RICEFW objects? Please choose the correct answer. Enhancement Delivery Custom Extensions Management Development Build Sprint Execution.
How many deliverables are a part of the Key Deliverable 'Project Initiation'? Four One Two Three.
Via which media does SAP provide Ready-to-run systems for SAP S/4HANA deployments? There are 2 correct answers to this question. SAP Solution Builder tool SAP Cloud Appliance Library SAP App Center Blu-ray disks.
Where can you find the Integration Content? There are 3 correct answers to this question. SAP Best Practices Explorer SAP Solution Manager SAP API Business Hub SAP Cloud Appliance library Cloud Integration Automation Service.
Which of the following are available in the initial SAP Methodologies JAM Page? There are 2 correct answers to this question. Roadmaps Task description Accelerators Summary.
What Solution Operations Framework can customers use to create a joint Business and IT organization, that will secure transparency and efficiency of SAP implementation, innovation, operation, and quality of business processes and systems? Please choose the correct answer. SAP Activate SAP Operations Control Center Business Transformation Management Methodology Customer Center of Expertise.
Which statements are part of the 5 Golden Rules for SAP S/4HANA Cloud, Single Tenant Edition? There are 2 correct answers to this question. Stick to the security standards of the customer organization. Use SAP Solution Manager 7.2 with Focused Build. Document deviations from Golden Rules for transparency and future use in upgrades. Foster a cloud mindset and adherence to the Fit-to-Standard approach.
Where can you find Data Migration templates? Please choose the correct answer. SAP Cloud Appliance Library SAP Best Practices Explorer SAP S/4HANA Migration Cockpit SAP Roadmap Viewer.
Which of the following is not correct about workstreams? There are 2 correct answers to this question. It can span phases It is a collection of related deliverables Workstreams are dependent on phase start and end It is assigned as an attribute to phases, deliverables and tasks.
Which of the following content best outlines the sequence of testing within the Application Design and Configuration work stream in the Realize phase? Please choose the correct answer. i. String test ii. Integration Test iii. User Acceptance Test i. String test ii. User Acceptance Test iii. Integration Test i. Data Migration ii. String test iii. User Acceptance Test i. Integration Test ii. User Acceptance Test iii. String test.
What do you do during post cutover? Please choose the correct answer. Setup Operational Support Conduct Organizational Readiness Check Perform the Verification Session of the SAP Going Live Check Perform Technical System Test.
In which phase should you create a Data Migration Strategy (LO) during a Selective Data Transition? Please choose the correct answer. Realize Deploy Explore Discover.
What is a Strategy Level 0 (LO) artifact? Please choose the correct answer. Project result that is developed solely by the partner Optional information that is NOT important for project activities Preliminary strategy developed by the customer to approach the project in a specific work stream Approach document that is developed by a united Project Team (partner + customer).
Which of the following is not a characteristic that the quality principles are based on? Please choose the correct answer. Experience of Typical Pitfalls Best Practices International standard SAP Quality Award example winners.
What does the Side-by-Side Extensibility Option mean? Please choose the correct answer. Have two SAP S/4HANA instances - one for standard code, and another for custom developments Context-aware SAP S/4HANA extensions, focused on tight integration Transfer reporting to BW/4HANA Extensibility based on the SAP Cloud Platform and published APls.
What is the order of artifacts within the Technical Architecture and Infrastructure workstream in the Prepare phase? Please choose the correct answer. Hardware specification from Hardware Vendor -> Technical Strategy -> Parameters Hardware Sizing calculation -> Hardware Sizing results Technical strategy -> Hardware specification from Hardware Vendor -> Parameters Hardware Sizing calculation -> Hardware Sizing results Technical Strategy -> Parameters Hardware Sizing calculation -> Hardware Sizing results -> Hardware Specification from Hardware Vendor Hardware specification from Hardware Vendor -> Parameters Hardware Sizing calculation -> Hardware Sizing results -> Technical Strategy.
What tool is used to synchronize changes between SAP ERP and SAP S/4HANA maintenance tracks? Please choose the correct answer. SAP Code Inspector Retrofit SAP Code Vulnerability Analyzer Business Process Change Analyzer.
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration? Please choose the correct answer. To create delta building blocks for complementary content To activate the Best Practices content To create customer-specific scope items To personalize activated, ready-to run business processes.
When does the project team receive formal confirmation that the user stories are completed to the satisfaction of the product owner? Please choose the correct answer. During the daily SCRUM meeting During the sprint retrospective During the sprint review During user acceptance testing.
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase? Please choose the correct answer. Go-Live scope is fixed on the first of January the following year. User Stories are in a Ready state for NO more than the first three Sprints. Project scope and planning are completed and final. Timelines of the Sprint may differ due to the workload.
Which of the following are not phases of the SAP Activate methodology? There are 2 correct answers to this question. Prepare Preparation Realize Go-Live & Support.
What is the purpose of the scrumboard? Please choose the correct answer. To visualize team progress To manage the resource load To document the results of integration testing To show the functional breakdown of the solution scope.
How do you achieve frequent checkpoints with the End User in an? There are 2 correct answers to this question. Solution Demo for Sprints Solution Review for Waves User Acceptance Test Demo the SAP Model Company.
Which of the following activities support the Realize Phase of a System Conversion journey to SAP S/4HANA On-Premise Edition? There are 2 correct answers to this question. Non-production systems migration Data aging configuration Custom code Adjustment planning Value determination.
In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project? Please choose the correct answer. Realize Explore Deploy Prepare.
Which of the following tools are specific to the Data Management work stream? There are 3 correct answers to this question. SAP Solution Manager SAP S/4HANA Migration Cockpit (for both SAP S/4HANA Cloud and SAP S/4HANA editions) SAP Data Services SAP Landscape Transformation SAP Roadmap Viewer.
What accelerator can help you document the Configuration Definition in the Explore phase? Please choose the correct answer. Backlog template Change Request template Data Definition Test Strategy.
Which of the following tools is used to install SAP S/4HANA. Please choose the correct answer. SAP Solution Manager Cloud Application Library SWPM (Software Provisioning Manager) Data Migration server.
Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase? There are 3 correct answers to this question. Solution Scope and Value Determination Validation Workshops Design for the Gaps and Deltas Data Migration Approach Baseline Build.
What does SAP Activate recommend to keep team members informed and aligned? Please choose the correct answer. Daily status meeting with project manager Daily team stand-up meeting Daily e-mail status updates to project manager Daily progress review meeting with sponsor.
Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in the Explore Phase? There are 2 correct answers to this question. Sprint Backlog Template Quality Gate Checklist RICEF Specification Template Solution Validation Workshop.
What are the responsibilities of the Project Team on level 4 in the picture below? There are 2 correct answers to this question. Identify and resolve issues and risks Set Project policy, standards and oversight Set business priorities, goals and objectives Perform status reporting and communication.
Arrange the following in the correct sequence of steps followed for a 'Fit to Standard' workshop. Please choose the correct answer. Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps Demonstrate Business Scenarios and Concepts, Review Best Practice Process Flow, Identify required configuration, Discuss how the process fit with customer requirements, Enable customer on execution of scenarios, Identify gaps Discuss how the process fit with customer requirements, Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration, Enable customer on execution of scenarios, Identify gaps Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts, Discuss how the process fit with customer requirements, Identify gaps, Identify required configuration, Enable customer on execution of scenarios.
What does the Content element of SAP Activate provide? There are 3 correct answers to this question. Business Processes Content Migration Content End-User guides Integration Content Functional Specifications for WRICEF development.
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps? Please choose the correct answer. Prepare Explore Deploy Realize.
What is SCRUM of SCRUMS? Please choose the correct answer. Frequent inspection of code and configuration prior to quality gates Integration meeting between the various project teams Alternative to regular SCRUM process for smaller teams Mechanism for gathering and validating requirements.
Which of the following are levels in the structure of an SAP Best Practices Solution Package? There are 2 correct answers to this question. Building Blocks Configuration Guides Business Process Scenarios Scope Items.
Why is there NO Sandbox system in the "New Implementation of SAP S/4HANA Cloud, Single Tenant Edition" transition path? Please choose the correct answer. Because the customer may use the SAP Model Company Because the Fit-to-Standard workshop is conducted using the Q-system Because SAP S/4HANA Cloud, Single Tenant Edition, contains predefined business processes which should NOT be changed Because the project team uses the DEV system to confirm solution fit and define delta requirements.
What is the basis for approving work results (signing Act of Acceptance) on a Project Phase level? Please choose the correct answer. Definition of Done for User Story Scrum of Scrums meeting decision Agreed and met Acceptance Criteria within Quality Gate Definition of Ready for Sprint.
What is the focus of a SCRUM of SCRUMS in an Agile context? Please choose the correct answer. Best Practice adoption Backlog management Integration topics Communication to the Project Management Office.
Which activity is part of the SAP Activate Methodology for a new implementation of SAP S/4HANA on-premise edition but NOT of the cloud edition? Please choose the correct answer. Technical System Test Unit Test User Acceptance Test End-to-End Integration Test.
Which criterion does the Product Owner use to sequence the product backlog? Please choose the correct answer. Business priority Complexity Relative effort Resource availability.
In SAP Activate, what tool is used in the during the Realize phase to make forecasts based on actual data? Please choose the correct answer. Release Plan Product Increment Project Plan Burn down Chart.
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud? Please choose the correct answer. SAP Support Marketplace SAP Transformation Navigator Implementation portal for SAP S/4HANA Cloud SAP Roadmap Viewer.
Which artifacts are created within Application Design and Configuration work stream in the Explore phase of the "New Implementation of SAP S/4HANA" transition path? There are 3 correct answers to this question. Roles and Authorizations Management Concept Project Procedure - Mock-up Modeling Detailed Design - Business Process Delta Requirements List - Register Organization Structure Specification.
In Which phase does the Transition to Operations work stream start? Please choose the correct answer. Deploy Prepare Realize Explore.
Which of the following are the key responsibilities of the Scrum Master? There are 3 correct answers to this question. Responsible for the project delivery Task initiator Leadership skill Team protection Team support.
Which tools does SAP Activate provide to support Guided Configuration? There are 3 correct answers to this question. Expert Configuration Solution Builder SAP Solution Composer Model Company Self Service Configuration.
What is a benefit of using Guided Configuration instead of the Implementation Guide? Please choose the correct answer. It ensures SAP updates do NOT conflict with customer configurations It ensures configuration is done using SAP Solution Manager It eliminates the need for Content Lifecycle Management It eliminates the need to generate transport requests for configuration settings.
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition? Please choose the correct answer. Waterfall approach Design-based Limited involvement of business stakeholders Start with executable content.
What are some of the key topics covered in the Customer Team Enablement workstream? There are 3 correct answers to this question. Project Management Solution Expertise Project Sourcing Approach Technical Expertise Planning skills.
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud' transition path? Please choose the correct answer. Simplification and Custom Code Impact Analysis Fit-to-standard Setup and Enablement Solution Validation and Delta Design.
How do you gain access to the SAP Activate Methodology Jam site? Please choose the correct answer. Join SAP S/4HANA group on SAP Community Network Send e-mail to SAP contact address Submit e-mail address via on-line form Register on SAP Service Marketplace.
What are the three elements of SAP Activate? There are 3 correct answers to this question. Tools Focused Build Content SAP Solution Manager Methodology.
What is the best target environment for a System Conversion journey is as described in the SAP Activate methodology? Please choose the correct answer. SAP Hybris SAP S/4HANA Cloud Edition Hybrid of SAP S/4HANA Cloud Edition and SAP S/4HANA On-Premise Edition SAP S/4HANA On-Premise Edition.
What can you do in the SAP Roadmap Viewer tool? Please choose the correct answer. Navigate detailed Solution Implementation Roadmaps. Comment on Deliverables and Tasks within Roadmaps. Download full roadmap content for offline navigation. Create a customer-specific version of a roadmap.
Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content? Please choose the correct answer. Navigate by Project Team Member Role Navigate by work stream Navigate by RACI matrix accountability Navigate by assigned Delivery Mode.
According to the Definition of Done, which activity must be completed for each sprint? Please choose the correct answer. Functionality must be released to the business The Solution must be built and configured in the development system (DEV) Functionality must be tested in the Quality system (QAS) End user training must be delivered.
How often will an upgrade be performed on an SAP S/4HANA Cloud, Single Tenant Edition environment? Please choose the correct answer. Schedule is defined by Service Level Agreement for SAP HANA Enterprise Cloud and SAP S/4HA NA Cloud, Single Tenant Edition Services Every year Every quarter One upgrade and two feature packs per year.
In which phase do you create an ordered list of everything that is known to be needed in the product"? Please choose the correct answer. Explore Realize Prepare Deploy.
When do you perform User Acceptance Testing during the Agile Build? Please choose the correct answer. Before Integration Testing After Integration Testing During each Firm-up Sprint After each Sprint.
What are some of the key characteristics of the implementation approach in SAP Activate Methodology? There are 3 correct answers to this question. Delta-based Cloud Ready Based on Ready-to-use Content Fixed scope On premise only.
In which phase of the SAP Activate Methodology does the team complete the System Assessment? Please choose the correct answer. Realize Prepare Explore Deploy.
Which of the following is not correct about the REALIZE phase? There are 2 correct answers to this question. The project team ensures that the build is meeting the business requirements. Detailed design workshops are held. The beginning of the Realize phase the team prepares a list of all the requirements in a backlog. The team prepares for operations so that the functionality can be brought live.
What is the difference between the "System Conversion and the "New Implementation of SAP S/4HANA" transition paths? There are 2 correct answers to this question. In the Realize phase, custom code is adjusted rather than developed for System Conversion. There are different upgrade cycles. SSCUls are used in System Conversion for configuring SAP S/4HANA through the Manage Your Solution app. In the Realize phase, data is converted and NOT migrated for System Conversion.
Which of the following are the pillars of SAP Activate? There are 3 correct answers to this question. SAP Launch Methodology SAP ASAP Methodology SAP Activate Methodology SAP Best Practices Guided Configuration.
Which key activities does the Guided Configuration support you with? There are 3 correct answers to this question. View solution scope Test configured processes Train new users Manage roles of configuration users Create test data.
Which activities are part of the Design and Configuration application of the SAP Activate methodology? There are 2 correct answers to this question. Perform Fit/Gap Analysis Conduct Scope Validation Confirm Integration prerequisites Schedule kick-off workshop.