Temario:

Which organizational structures are required for network activities?There are 3 correct answers to this question. Company code. Sales organization. Plant. Controlling area. Operating concern.

Which sales documents can update planned revenues on WBSelements?There are 2 correct answers to this question. Sales order. Billing. Inquiry. Quota.

Which of the following business processes do NOT lead to thebooking of actual costs to an object?There are 2 correct answers to this question. Recording of external services in the service entry sheet. Goods receipt into valuated project stock. Goods receipt into unvaluated project stock. Goods receipt of a non-stock item.

You want to allocate overhead rates to a WBS element. What mustyou assign to the WBS element?. Investment profile. Settlement rule. Results analysis key. Costing sheet.

A component is assigned to a network activity. What are theprerequisites to generate project stock reservations?There are 3 correct answers to this question. A procurement indicator must be assigned to the activity. The material master of the component must permit project stock management. The network is assigned to a sales order item. The network activity is assigned to a WBS element. The Project Stock indicator is set in the project definition (non-valuated orvaluated).

You are using WBS elements and activities are NOT assigned. Whichstatements apply to the maintenance of the actual start and finish?There are 2 correct answers to this question. You can always maintain the actualstart and finish date of a WBS element. You can always maintain the actual start if the WBS element has the status“Released” or “Partially released”. You can only maintain the actual start of a WBS element if the finish date is notmaintained. You can only maintain the actual finish if all lower-level WBS elements have anactual finish date and the status of the WBS element is “Released”.

What could be a reason to use expert mode in the valuation methodfor results analysis?. Valuation in different currencies. Usage of different line IDs. Assignments of different accounts for postings to financial accounting. Billing WBS elements belonging to different company code.

How are earliest dates and latest dates of activities scheduled?. Earliest dates are scheduled by backward scheduling, and latest dates by forwardscheduling. Earliest dates and latest dates are scheduled by forward scheduling. Earliest dates are scheduled by backward scheduling, and latest dates by copyingthe earliest dates. Earliest dates are scheduled by forward scheduling, and latest dates by backwardscheduling.

You want to determine the planned costs for an internally processedactivity. Which data do you need?There are 2 correct answers to this question. Activity type. Duration. Work. Profit center.

What is copied when transferring a simulation version back to anoperative project?There are 3 correct answers to this question. Plan cost. WBS elements. Actual wor. Maintenance orders assigned to the project. Network activiti.

You used hierarchical revenue planning to plan revenues for WBSelements manually. The cost element report for planned revenues does not show any revenues at all. What is the reason for this?. The manual hierarchical revenue planning will be displayed only if expert mode isactivated. Cost element reports can display costs but not revenues. The manual hierarchical revenue planning has no reference to cost elements. Cost element reports display integrated planning only.

Where can you assign the user status profile for WBS elements?There are 3 correct answers to this question. In the operative WBS element. In the project profile. In the project version. In the project definition of a standard WBS. In the project type.

Which object is used to allocate the costs from a claim to theproject structure?. Claim. Network activity. WBS element. Internal order.

Your customer wants to use requirements grouping in SAP ProjectSystem. What are the prerequisites for requirements grouping of materials?There are 2 correct answers to this question. The materials must allow sales order or project stock. The exact lotsize procedure must be. The procurement type of the material must be internal. An MRP group must be assigned.

How can you record external service activities with service masterdata?There are 2 correct answers to this question. Confirm the network activity for externalservices. Confirm the activities in the Cross-Application Time Sheet (CATS). Post a goodsreceipt in the goods movement application (MIGO). Create a service entry sheet.

You plan an activity that starts on February 1 and finishes onFebruary 28. For this activity, you want to define a milestone for February 10which should NOT be changed through scheduling.What do you recommend for milestone definition?. Enter 10 days as duration. Enter an offset of 10 days to the start date of the activity. Enter February 10 as fixed date. Enter an offset of -18 days to the finish date of the activity.

You want to extrapolate basic dates from lower to higher-level WBSelements. The duration of higher-level elements should NOT be reduced. Whichplanning method do you choose?. Bottom-up. Strict bottom-up. Free planning. Top-down.

Which statement is valid regarding networks?There are 2 correct answers to this question. Relationships can be used to connect activities of different networks. Material components can be assigned to activity elements. A network activity can be assigned to several WBS elements. A network can be activity-account-assigned and header-account-assigned.

Where can you define a network as "header-account-assigned" or"activity-account-assigned"?. Parameters for the network type. Project profile. Network profile. Network type.

Which planning method can prevent further rescheduling ofactivities?. Workforce planning. Capacity leveling. Partial confirmation of activities. Capacity requirements activation.

Which orders or documents can be displayed in Project-OrientedProcurement (ProMan)?There are 2 correct answers to this question. Sales order items. Purchase order items. Reservations. Internal orders.

You want to create a reservation for a material component assignedto a network activity. However, after releasing and saving the activity, noreservation is created.What are some possible reasons for the missing reservation?There are 2 correct answers to this question. The material master is set to external procurement. The indicator Reservation/Purchase Requisition indicator for the materialcomponent assigned to the activity is set to "never". The availability check for material components indicates missing parts. The material is assigned to the activity as a non-stock material.

Which object is relevant in assembly processing to create anassembly order for the SD document?. Item category. Requirement class. Control key. Project profile.

Which of the following factors influence the scheduling of internalprocessing activities?There are 3 correct answers to this question. Whether the work for the internal activity is greater than its duration. The factory calendar in the work center used for the internal processing activity. The relationships between activity elements. An activated Scheduling indicator in the control key of the internal processingactivity. The unit (for example, hour, day) of the field Normal Duration field of the activity.

You want to assign milestones to WBS elements. For what can youuse these milestones?There are 2 correct answers to this question. To start workflow tasks. For trend analysis. To transfer the actual date to the billing plan. To set an actual finish date for WBS elements.

Where do you maintain the length of the project ID?. Project profile. Special characters. Project type. Project coding mask.