In your logistics project, you want to carry out the internal projectwork as soon as possible. What do you have to maintain in capacityrequirements planning?Please choose the correct answer. Capacity planner group in the network header. Control key of an activity. Scheduling and distribution key. Scheduling and capacity category.

You want to make sure that certain tasks must start on a givendate. Where can you maintain constraints for start dates?Please choose the correct answer. Milestone. Activity. Activity element. Network header.

Where do you maintain the length of the project ID?Please choose the correct answer. Project profile. Special characters. Project type. Project coding mask.

You have implemented automatic requirements grouping forprojects. Once you check the materials cabin and fork you realize that therequirements are grouped for cabin but not for fork.What might be the reason?Please choose the correct answer. The grouping indicator of the top WBS element is set to a single MRP Group. he network is set to no grouping for specific MRP Groups. The MRP Group for fork is deactivated for grouping. The project definition is set to no project stock.

You want to extrapolate basic dates from lower to higher-level WBSelements. The duration of higher-level elements should NOT be reduced. Whichplanning method do you choose?Please choose the correct answer. Bottom-up. Strict bottom-up. Free planning. Top-down.

What functionality can you perform with activity elements?Please choose the correct answer. Create relationships. Assign work centers and capacities. Schedule WBS elements. Assign materia.

Which of the following apply to dynamic item processor (DIP)?There are 3 correct answers to this question. Sales prices are maintained in the DIP profile. Usage of cost elements is mandatory. Sources can be based on line items. DIP is used to create a quotation. Material determination is mandatory.

How can you grant individual authorization for WBS elements andnetworks?Please choose the correct answer. Define a user status to lock the business transaction Update Project. Set the system statusto "Lock Master Data". Activate access control lists (ACL) for the user master record. Activate access control lists (ACL) for the project profile and the network profile.

How are earliest dates and latest dates of activities scheduled?Please choose the correct answer. Earliest dates are scheduled by backward scheduling, and latest dates by forwardscheduling. Earliest dates and latest dates are scheduled by forward scheduling. Earliest dates are scheduled by backward scheduling, and latest dates by copyingthe earliest dates. Earliest dates are scheduled by forward scheduling, and latest dates by backwardscheduling.

Which of the following data can be maintained in a standardnetwork?There are 3 correct answers to this question. Material components. Basic dates for activities. Relationships. Document information records. Internally processed activities.

You are working with predefined project coding masks to createprojects. Which of the following statements apply?There are 2 correct answers to this question. You can use an indicator to determine that only coded project numbers may beused within SAP Project System. You can only use numbers for a project coding mask definition. You can use the same coding mask forstandard projects and operative projects. You can shorten the project mask even when there are existing projects.

What is copied when transferring a simulation version back to anoperative project?There are 3 correct answers to this question. Plan costs. WBS elements. Actual work. Maintenance orders assigned to the project. Network activities.

You are using WBS elements and activities are NOT assigned. Whichstatements apply to the maintenance of the actual start and finish?There are 2 correct answers to this question. You can always maintain the actualstart and finish date of a WBS element. You can always maintain the actual start if the WBS element has the status“Released” or “Partially released”. You can only maintain the actual start of a WBS element if the finish date is notmaintained. You can only maintain the actual finish if all lower-level WBS elements have anactual finish date and the status of the WBS element is “Released”.

You use networks and internal activities in your project. You haveactivated capacity requirements and notice that one work center is overloaded.You have no authorization to change the work center.How can you reduce the overload of the work center?There are 2 correct answers to this question. rigger automatic capacity leveling inside the project planning board. Shift activities backward orforward on the time axis where more capacities areavailable. Maintain subordinate internal activity elements assigned to other work centers. Increase the capacities of the work center in the project planning board.

You have created an internally-processed network activity, and assigned a workcenter and the work. After saving, you discover that no planned costs aredisplayed in the cost element report for the activity.What could be the reason?There are 3 correct answers to this question. The Determine Costs indicator in the network header rules out planned costcalculation. The activity output price for the activity type and cost center assigned to the workcenter is not maintained. The formula for costing in the work center is incorrect. Integrated planning for the network is active. The duration is missing in the activity.

Which organizational structures are required for network activities?There are 3 correct answers to this question. Company code. Sales organization. Plant. Controlling area. Operating concern.

ow can you confirm the working hours of different work centersfor a single activity?Please choose the correct answer. Enter direct activity allocation assigning multiple work centers. Assign multiple work centersto the activity. Enter multiple work centers within a single confirmation. Create multiple confirmations for the activity and use the appropriate work centerfor each confirmation.

Where can you assign the user status profile for WBS elements?There are 3 correct answers to this question. In the operative WBS element. In the project profile. In the project version. In the project definition of a standard WBS. In the project type.

Which report can use user-specific layouts?Please choose the correct answer. Enhanced individual overview. Hierarchical report. Line item report. Cost element report.

Which sales documents can update planned revenues on WBSelements?There are 2 correct answers to this question. Sales order. Billing. Inquiry. Quotation.

When you create a service activity in your network, what data canbe entered?There are 3 correct answers to this question. Service specification. Material master within service specification. Vendor. Service purchase order number. Overall limit (maximum value of all unplanned services).

Most of the reports in SAP Project System can be refreshed withoutexiting or closing the report. Which report must be restarted to update thedisplayed data?Please choose the correct answer. Hierarchical Reports. Individual Overviews. Reports by Cost Element. Structure Overview.

Where can you define a network as "header-account-assigned" or"activity-account-assigned"?Please choose the correct answer. Parameters for the network type. Project profile. Network profile. Network type.

A service company uses project management and they complainthat the system does not prevent their project managers from exceeding theirbudgets.What actions do you have to take to solve the problem?Please choose the correct answer. Activate availability control in the assigned budget profile. Define the tolerancelimitsin customizing. Activate commitment management in the project definition. Enter the budget in themaster data of the top WBS element. Activate availability control for the WBS elements. Define the tolerance limits oneach WBS element. Activate availability control for projects in the controlling area. Enter the plan datafor each WBS element.

For which objects can billing plans be created?There are 2 correct answers to this question. Sales order items. Milestones. Project definition. WBS elements.

Which sets of dates can be used to schedule networks?There are 2 correct answers to this question. Basic dates. Forecast dates. Baseline dates. Planned dates.

You want to set up the field selection of the Cross-Application TimeSheet (CATS) in Customizing. Which influencing field do you use?Please choose the correct answer. Project profile. Network profile. Network type. Data entry profile.